Job Card JC-2026-3067

Item 1 — Feature stringer stair — plate & CHS
Demo 05 Oct 2026
Stage
Complete
ITP progress
8 / 8
hold points 4 / 4 signed
Job value
$136,184.90
Due
27 Sep 2026
High
Workshop route
✓ Queued
✓ Cutting
✓ Fabrication
✓ Welding
✓ Finishing
● Complete
Complete — heat number minted
Details
PRJ-2026-407 · Adelaide Airport Ltd
Quantity1
MaterialMild Steel
FinishSatin 316 finish
Assigned toDean Roberts
Due date27 Sep 2026
Heat / traceability no.HT-40629
ProjectPRJ-2026-407 · Item 1
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
8 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
01 Oct 2026 · 08:15
2
Material certificates / heat numbers recorded
Passed
Dean Roberts
01 Oct 2026 · 08:15
3
Cut list & set-out checked
Passed
Anthony Reid
28 Sep 2026 · 13:05
4
Fit-up inspection before welding
HOLD POINT
Passed
Yang Li
27 Sep 2026 · 13:05
5
Weld visual inspection to AS/NZS 1554.1
Passed
Dean Roberts
23 Sep 2026 · 13:05
6
Dimensional check against drawing
Passed
Anthony Reid
01 Oct 2026 · 13:05
7
Surface prep & coating inspection
HOLD POINT
Passed
Yang Li
30 Sep 2026 · 13:05
8
Final release to site
HOLD POINT
Passed
Yang Li
02 Oct 2026 · 13:05
Customer
Adelaide Airport Ltd
Adelaide Airport SA
Project
PRJ-2026-407 · Job 26-1054
Project item
Item 1 — Feature stringer stair — plate & CHS
PRJ-2026-407 · register status Invoiced
Allowed vs actual hours
Factory391 h / 415 h 94%
Site245 h / 269 h 91%
Office86 h / 93 h 92%
Labour & time →
Recent time on this item
Yang Li
11 Sep · Office · 08:00–16:30
8 h
Mitch Daly
11 Sep · Factory · 06:30–15:00
8 h
Josh Kerr
11 Sep · Factory · 06:30–15:00
8 h
Ben Hartley
11 Sep · Site · 06:00–14:30
8 h
Peter Voulgaris
10 Sep · Factory · 06:30–15:00
8 h
Peter Voulgaris
10 Sep · Factory · 06:30–15:00
8 h
Ben Hartley
10 Sep · Site · 06:00–14:30
8 h
Peter Voulgaris
09 Sep · Factory · 06:30–15:00
8 h
Peter Voulgaris
09 Sep · Factory · 06:30–15:00
8 h
Tyler Hocking
09 Sep · Site · 06:00–14:30
8 h
Mitch Daly
08 Sep · Factory · 06:30–15:00
8 h
Dean Roberts
08 Sep · Factory · 06:30–15:00
8 h