Workshop load — open job cards
Dean Roberts3 · $67.2k
Anthony Reid6 · $188.3k
Peter Voulgaris5 · $310.8k
Luke Bianco0 · $0
Master project schedule
DetailingFabricationFinishingSite InstallComplete
Project
24 Aug
31 Aug
07 Sep
14 Sep
21 Sep
28 Sep
05 Oct
12 Oct
19 Oct
26 Oct
02 Nov
09 Nov
16 Nov
23 Nov
30 Nov
Value
PRJ-2026-401Fabrication
Louvre screens & sunhoods — Airport carpark facade
Badge Constructions
$156.6k
PRJ-2026-407Complete
Feature entry staircase & balustrade — terminal
Adelaide Airport Ltd
$222.9k
PRJ-2026-404Fabrication
Stainless handrail & grab-rail package — hospital
Sarah Constructions
$51.2k