Live contract value (ex GST)
$1.43M
8 projects · 29 items
Claimed to date
$698.9k
49% of live contracts
Overdue items
0
$0 past due, not invoiced
Items over allowed hours
1
against quote-book allowances
26-1057 PRJ-2026-409 Mossop Construction + Interiors Feature stair & balustrades — Kent Town apartments
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Feature stair — folded plate stringers | $69,905.35 | 40.3% | 0% · $0 | MCI-2026-0418 | 396 / 8 h | 12 Oct | |
| 2 | Balustrade 1 — apartment balconies (82 m) | $61,582.00 | 35.5% | 10% · $6.2k | MCI-2026-0418 | 352 / 0 h | 12 Oct | |
| 3 | Balustrade 2 — common stair (30 m) | $22,681.60 | 13.1% | 50% · $11.3k | MCI-2026-0418 | 129 / 67.7 h | 26 Oct | |
| 4 | Bin store gates & screens | $19,144.15 | 11% | 0% · $0 | MCI-2026-0418 | 104 / 8 h | 09 Nov | |
| Project total (4 items) | $173,313.10 | 100% | 10% · $17.5k | 981 / 83.7 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Balustrade 1 — mezzanine edge balustrade (64 m) | $94,705.55 | 21.7% | 100% · $94.7k | HY-AIR7-PO-4471 | 539 / 513 h | 21 Sep | |
| 2 | Balustrade 2 — stair balustrade, hangar office (38 m) | $58,786.35 | 13.5% | 70% · $41.2k | HY-AIR7-PO-4471 | 336 / 369.5 h | 19 Oct | |
| 3 | Handrails — galvanised to apron access (90 m) | $33,491.00 | 7.7% | 70% · $23.4k | HY-AIR7-PO-4471 | 188 / 161.7 h | 26 Oct | |
| 4 | External bollards — galvanised, apron (24 no) | $27,277.20 | 6.3% | 50% · $13.6k | HY-AIR7-PO-4471 | 151 / 128.2 h | 19 Oct | |
| 5 | Perforated panelling — plant screen enclosure | $71,381.65 | 16.4% | 40% · $28.6k | HY-AIR7-PO-4471 | 407 / 142.4 h | 02 Nov | |
| 6 | Ships ladders, cages & roof access platform | $56,442.45 | 12.9% | 10% · $5.6k | HY-AIR7-PO-4471 | 320 / 12 h | 09 Nov | |
| 7 | Grating walkways & landings — services gantry | $83,497.70 | 19.1% | 0% · $0 | HY-AIR7-PO-4471 | 473 / 17 h | 09 Nov | |
| V1 | Additional galvanised bollards to apron (6 no) | $10,654.00 | 2.4% | 0% · $0 | VO-01 | 58 / 4 h | 02 Nov | |
| Project total (8 items) | $436,235.90 | 100% | 47% · $207.1k | 2472 / 1347.8 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Marine-grade access platform & landings — galv | $161,305.95 | 56.9% | 90% · $145.2k | FP-77341 | 919 / 676.8 h | 12 Oct | |
| 2 | Fixed & tidal ladders with safety cages | $92,927.00 | 32.8% | 100% · $92.9k | FP-77341 | 527 / 516 h | 21 Sep | |
| 3 | Self-closing gates & handrail — 140m | $29,481.45 | 10.4% | 70% · $20.6k | FP-77341 | 167 / 145.6 h | 12 Oct | |
| Project total (3 items) | $283,714.40 | 100% | 91% · $258.7k | 1613 / 1338.4 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Galvanised balustrade to AS 1657 — 64m | $13,954.85 | 18.8% | 0% · $0 | SAW-4500912 | 76 / 4 h | 12 Oct | |
| 2 | Access walkway with FRP grating & kickplate | $51,016.15 | 68.6% | 10% · $5.1k | SAW-4500912 | 291 / 4 h | 19 Oct | |
| 3 | Loose fixings, chemsets & anchors — supply | $9,400.00 | 12.6% | 30% · $2.8k | SAW-4500912 | 0 / 0 h | 26 Oct | |
| Project total (3 items) | $74,371.00 | 100% | 11% · $7.9k | 367 / 8 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | 316 stainless handrail to stairs — satin finish | $28,840.85 | 59.3% | 90% · $26.0k | SC-PO-30552 | 163 / 147.5 h | 12 Oct | |
| 2 | Grab rails & wall-mounted rails (DDA) | $11,919.65 | 24.5% | 50% · $6.0k | SC-PO-30552 | 64 / 36.5 h | 19 Oct | |
| 3 | Stainless mesh infill panels | $7,870.60 | 16.2% | 90% · $7.1k | SC-PO-30552 | 41 / 34.5 h | 19 Oct | |
| Project total (3 items) | $48,631.10 | 100% | 80% · $39.0k | 268 / 218.5 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Gantry structural steel — UB/UC + bracing | $160,677.95 | 69.2% | 30% · $48.2k | NYR-PP-23019 | 919 / 213.9 h | 12 Oct | |
| 2 | Walkway, handrail & kickplate to gantry | $71,595.15 | 30.8% | 30% · $21.5k | NYR-PP-23019 | 407 / 140.9 h | 12 Oct | |
| Project total (2 items) | $232,273.10 | 100% | 30% · $69.7k | 1326 / 354.8 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Access platform 3.6 x 2.4m — grating & handrail | $26,003.65 | 65.9% | 80% · $20.8k | CE-11872 | 148 / 133.9 h | 12 Oct | |
| 2 | Caged ladder 5.2m with landing | $13,425.95 | 34.1% | 100% · $13.4k | CE-11872 | 73 / 70 h | 07 Sep | |
| Project total (2 items) | $39,429.60 | 100% | 87% · $34.2k | 221 / 203.9 h |
| Item | Description | Status | Value | % contract | Claimed | Client PO | Allowed / actual hrs | Due w/c |
|---|---|---|---|---|---|---|---|---|
| 1 | Aluminium louvre screen frames & blades — Type A | $48,680.50 | 34.7% | 30% · $14.6k | BC-24-1187 | 274 / 128.8 h | 12 Oct | |
| 2 | Perimeter sunhoods & flashings — folded sheet | $38,148.25 | 27.2% | 50% · $19.1k | BC-24-1187 | 214 / 126.1 h | 19 Oct | |
| 3 | Louvre screens — Type B to stair core | $21,297.25 | 15.2% | 10% · $2.1k | BC-24-1187 | 122 / 5 h | 19 Oct | |
| 4 | Site install, access & fixings | $32,109.95 | 22.9% | 90% · $28.9k | BC-24-1187 | 183 / 171.7 h | 26 Oct | |
| Project total (4 items) | $140,235.95 | 100% | 46% · $64.7k | 793 / 431.6 h |
Completed projects stay in the register for history and reporting.
| Job | Project | Client | Title | PM | Items | Contract | Claimed | Hours allowed / actual |
|---|---|---|---|---|---|---|---|---|
| 26-1081 | PRJ-2026-427 | Century Engineering | Louvre screens & architectural mesh | Craig Pearce | 2 | $175,926.70 | 100% | 1004 / 960 h |
| 26-1080 | PRJ-2026-426 | Sarah Constructions | Access platforms & walkways — WWTP | Craig Pearce | 4 | $265,611.40 | 100% | 1512 / 1433 h |
| 26-1079 | PRJ-2026-425 | Hansen Yuncken | Balustrade & handrail package — apartments | Craig Pearce | 4 | $301,472.05 | 100% | 1716 / 1677 h |
| 26-1078 | PRJ-2026-424 | Seeley International | Structural steel & stair — warehouse extension | Craig Pearce | 4 | $329,376.70 | 100% | 1868 / 1832 h |
| 26-1076 | PRJ-2026-423 | Mossop Construction + Interiors | Loading dock steel & bollards | Craig Pearce | 4 | $339,985.75 | 100% | 1932 / 1925 h |
| 26-1075 | PRJ-2026-422 | Dept for Infrastructure & Transport | Handrail package — hospital fitout | Matthew Warren | 3 | $131,166.95 | 100% | 738 / 732 h |
| 26-1074 | PRJ-2026-421 | Dept for Infrastructure & Transport | Cable ladder support steel | Craig Pearce | 3 | $224,395.05 | 100% | 1275 / 1221 h |
| 26-1071 | PRJ-2026-420 | Flinders Ports | Grandstand balustrade & rails | Matthew Warren | 2 | $225,678.85 | 100% | 1290 / 1321 h |
| 26-1070 | PRJ-2026-419 | Detmold Group | Tank access stairs & landings | Craig Pearce | 2 | $236,144.75 | 100% | 1348 / 1305 h |
| 26-1069 | PRJ-2026-418 | Bianco Construction | Canopy & entry steel — retail | Craig Pearce | 3 | $249,990.80 | 100% | 1431 / 1392 h |
| 26-1068 | PRJ-2026-417 | Detmold Group | Pedestrian bridge steel & balustrade | Craig Pearce | 2 | $80,017.35 | 100% | 454 / 440 h |
| 26-1065 | PRJ-2026-416 | Seeley International | Feature staircase & balustrade | Matthew Warren | 2 | $264,833.00 | 100% | 1512 / 1462 h |
| 26-1064 | PRJ-2026-415 | Hansen Yuncken | Conveyor support steel | Craig Pearce | 4 | $105,003.70 | 100% | 592 / 578 h |
| 26-1063 | PRJ-2026-414 | Badge Constructions | Marine handrail & ladder package | Matthew Warren | 4 | $308,324.20 | 100% | 1752 / 1711 h |
| 26-1061 | PRJ-2026-413 | Adelaide Airport Ltd | Louvre screens & architectural mesh | Craig Pearce | 2 | $346,335.45 | 100% | 1980 / 1957 h |
| 26-1060 | PRJ-2026-412 | Flinders Ports | Access platforms & walkways — WWTP | Craig Pearce | 2 | $49,209.80 | 100% | 274 / 268 h |
| 26-1059 | PRJ-2026-411 | Bianco Construction | Balustrade & handrail package — apartments | Craig Pearce | 4 | $218,671.80 | 100% | 1244 / 1203 h |
| 26-1058 | PRJ-2026-410 | SAGE Automation | Structural steel & stair — warehouse extension | Matthew Warren | 2 | $60,158.25 | 100% | 340 / 332 h |
| 26-1054 | PRJ-2026-407 | Adelaide Airport Ltd | Feature entry staircase & balustrade — terminal | Matthew Warren | 3 | $195,734.65 | 100% | 1115 / 1049 h |
Revenue vs gross profit by month RevenueGross profitScheduled (next 3 months)
| May 26 | Jun 26 | Jul 26 | Aug 26 | Sep 26 | Oct 26 · MTD | Nov 26 | Dec 26 | Jan 27 | |
|---|---|---|---|---|---|---|---|---|---|
| Claimed revenue | $1.07M | $695.5k | $791.8k | $877.4k | $1.10M | $273.9k | — | — | — |
| Scheduled claims (draft) | — | — | — | — | — | $533.4k | $195.8k | — | — |
| Labour (factory & site) | ≈$332.3k | $194.2k | $238.4k | $258.7k | $341.0k | $9.3k | ≈$85.8k | ≈$0 | ≈$0 |
| Office | ≈$54.0k | $31.5k | $42.3k | $43.5k | $66.3k | $1.1k | ≈$14.3k | ≈$0 | ≈$0 |
| Materials | ≈$266.8k | $172.8k | $246.0k | $194.0k | $323.0k | $63.0k | ≈$66.9k | ≈$0 | ≈$0 |
| Contractors & services | ≈$96.7k | ≈$62.4k | ≈$71.5k | ≈$60.8k | ≈$96.4k | ≈$84.2k | ≈$24.3k | ≈$0 | ≈$0 |
| Gross profit | $322.7k | $234.6k | $193.7k | $320.4k | $269.3k | $116.2k | $4.6k | $0 | $0 |
| GP % | 30% | 34% | 24% | 37% | 25% | 42% | 2% | — | — |
Revenue is progress claims issued (not draft) by claim date; the next three months use scheduled draft claims. Labour and office are clocked hours × each person's cost rate; materials are purchase orders by PO date. ≈ marks figures taken from quote-book item allowances by the month each item falls due — used for contractors & services (contract services on the item sheets), and for labour, office and materials in months before clocked hours and purchase orders were on record. The current month is month-to-date. Claimed $4.81M · scheduled $729.3k across the window.
Detailing 2 · $247,684.10
PRJ-2026-409 PayApps
Feature stair & balustrades — Kent Town apartments
26-1057 · Mossop Construction + Interiors $173,313.10
PRJ-2026-405
Balustrade & FRP walkway — pump station upgrade
26-1045 · SA Water $74,371.00
—
Fabrication 3 · $808,744.95
PRJ-2026-408 PayApps
AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
26-1056 · Hansen Yuncken $436,235.90
PRJ-2026-403
Conveyor gantry & support steel — Port Pirie
26-1043 · Nyrstar Port Pirie $232,273.10
PRJ-2026-401
Louvre screens & sunhoods — airport carpark facade
26-1041 · Badge Constructions $140,235.95
—
Finishing 1 · $48,631.10
PRJ-2026-404 PayApps
Stainless handrail & grab-rail package — hospital
26-1044 · Sarah Constructions $48,631.10
—
Site Install 2 · $323,144.00
PRJ-2026-406
Berth access platform, ladders & gates — marine
26-1053 · Flinders Ports $283,714.40
PRJ-2026-402
Access platform & caged ladder — plant upgrade
26-1042 · Century Engineering $39,429.60
—
Complete 19 · $4,108,037.20
PRJ-2026-427
Louvre screens & architectural mesh
26-1081 · Century Engineering $175,926.70
PRJ-2026-426 PayApps
Access platforms & walkways — WWTP
26-1080 · Sarah Constructions $265,611.40
PRJ-2026-425 PayApps
Balustrade & handrail package — apartments
26-1079 · Hansen Yuncken $301,472.05
PRJ-2026-424
Structural steel & stair — warehouse extension
26-1078 · Seeley International $329,376.70
PRJ-2026-423 PayApps
Loading dock steel & bollards
26-1076 · Mossop Construction + Interiors $339,985.75
PRJ-2026-422
Handrail package — hospital fitout
26-1075 · Dept for Infrastructure & Transport $131,166.95
PRJ-2026-421
Cable ladder support steel
26-1074 · Dept for Infrastructure & Transport $224,395.05
PRJ-2026-420
Grandstand balustrade & rails
26-1071 · Flinders Ports $225,678.85
PRJ-2026-419
Tank access stairs & landings
26-1070 · Detmold Group $236,144.75
PRJ-2026-418
Canopy & entry steel — retail
26-1069 · Bianco Construction $249,990.80
PRJ-2026-417
Pedestrian bridge steel & balustrade
26-1068 · Detmold Group $80,017.35
PRJ-2026-416
Feature staircase & balustrade
26-1065 · Seeley International $264,833.00
PRJ-2026-415 PayApps
Conveyor support steel
26-1064 · Hansen Yuncken $105,003.70
PRJ-2026-414
Marine handrail & ladder package
26-1063 · Badge Constructions $308,324.20
PRJ-2026-413
Louvre screens & architectural mesh
26-1061 · Adelaide Airport Ltd $346,335.45
PRJ-2026-412
Access platforms & walkways — WWTP
26-1060 · Flinders Ports $49,209.80
PRJ-2026-411
Balustrade & handrail package — apartments
26-1059 · Bianco Construction $218,671.80
PRJ-2026-410
Structural steel & stair — warehouse extension
26-1058 · SAGE Automation $60,158.25
PRJ-2026-407
Feature entry staircase & balustrade — terminal
26-1054 · Adelaide Airport Ltd $195,734.65
—