Co-Create

Project Register

8 live projects · 29 items · $1.43M contract value
Demo 05 Oct 2026
Live contract value (ex GST)
$1.43M
8 projects · 29 items
Claimed to date
$698.9k
49% of live contracts
Overdue items
0
$0 past due, not invoiced
Items over allowed hours
1
against quote-book allowances
OfficeFactorySiteInvoicedCancelled
26-1057 PRJ-2026-409 Mossop Construction + Interiors Feature stair & balustrades — Kent Town apartments
PM Craig Pearce Detailing PayApps Contract $173,313.10 Claimed 10% $17,499.00
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Feature stair — folded plate stringers $69,905.35 40.3% 0% · $0 MCI-2026-0418
396 / 8 h
12 Oct
2 Balustrade 1 — apartment balconies (82 m) $61,582.00 35.5% 10% · $6.2k MCI-2026-0418
352 / 0 h
12 Oct
3 Balustrade 2 — common stair (30 m) $22,681.60 13.1% 50% · $11.3k MCI-2026-0418
129 / 67.7 h
26 Oct
4 Bin store gates & screens $19,144.15 11% 0% · $0 MCI-2026-0418
104 / 8 h
09 Nov
Project total (4 items) $173,313.10100% 10% · $17.5k
981 / 83.7 h
26-1056 PRJ-2026-408 Hansen Yuncken AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
PM Craig Pearce Fabrication PayApps Contract $436,235.90 Claimed 47% $207,135.22
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Balustrade 1 — mezzanine edge balustrade (64 m) $94,705.55 21.7% 100% · $94.7k HY-AIR7-PO-4471
539 / 513 h
21 Sep
2 Balustrade 2 — stair balustrade, hangar office (38 m) $58,786.35 13.5% 70% · $41.2k HY-AIR7-PO-4471
336 / 369.5 h
19 Oct
3 Handrails — galvanised to apron access (90 m) $33,491.00 7.7% 70% · $23.4k HY-AIR7-PO-4471
188 / 161.7 h
26 Oct
4 External bollards — galvanised, apron (24 no) $27,277.20 6.3% 50% · $13.6k HY-AIR7-PO-4471
151 / 128.2 h
19 Oct
5 Perforated panelling — plant screen enclosure $71,381.65 16.4% 40% · $28.6k HY-AIR7-PO-4471
407 / 142.4 h
02 Nov
6 Ships ladders, cages & roof access platform $56,442.45 12.9% 10% · $5.6k HY-AIR7-PO-4471
320 / 12 h
09 Nov
7 Grating walkways & landings — services gantry $83,497.70 19.1% 0% · $0 HY-AIR7-PO-4471
473 / 17 h
09 Nov
V1 Additional galvanised bollards to apron (6 no) $10,654.00 2.4% 0% · $0 VO-01
58 / 4 h
02 Nov
Project total (8 items) $436,235.90100% 47% · $207.1k
2472 / 1347.8 h
26-1053 PRJ-2026-406 Flinders Ports Berth access platform, ladders & gates — marine
PM Matthew Warren Site Install Contract $283,714.40 Claimed 91% $258,739.40
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Marine-grade access platform & landings — galv $161,305.95 56.9% 90% · $145.2k FP-77341
919 / 676.8 h
12 Oct
2 Fixed & tidal ladders with safety cages $92,927.00 32.8% 100% · $92.9k FP-77341
527 / 516 h
21 Sep
3 Self-closing gates & handrail — 140m $29,481.45 10.4% 70% · $20.6k FP-77341
167 / 145.6 h
12 Oct
Project total (3 items) $283,714.40100% 91% · $258.7k
1613 / 1338.4 h
26-1045 PRJ-2026-405 SA Water Balustrade & FRP walkway — pump station upgrade
PM Craig Pearce Detailing Contract $74,371.00 Claimed 11% $7,921.62
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Galvanised balustrade to AS 1657 — 64m $13,954.85 18.8% 0% · $0 SAW-4500912
76 / 4 h
12 Oct
2 Access walkway with FRP grating & kickplate $51,016.15 68.6% 10% · $5.1k SAW-4500912
291 / 4 h
19 Oct
3 Loose fixings, chemsets & anchors — supply $9,400.00 12.6% 30% · $2.8k SAW-4500912
0 / 0 h
26 Oct
Project total (3 items) $74,371.00100% 11% · $7.9k
367 / 8 h
26-1044 PRJ-2026-404 Sarah Constructions Stainless handrail & grab-rail package — hospital
PM Craig Pearce Finishing PayApps Contract $48,631.10 Claimed 80% $39,000.15
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 316 stainless handrail to stairs — satin finish $28,840.85 59.3% 90% · $26.0k SC-PO-30552
163 / 147.5 h
12 Oct
2 Grab rails & wall-mounted rails (DDA) $11,919.65 24.5% 50% · $6.0k SC-PO-30552
64 / 36.5 h
19 Oct
3 Stainless mesh infill panels $7,870.60 16.2% 90% · $7.1k SC-PO-30552
41 / 34.5 h
19 Oct
Project total (3 items) $48,631.10100% 80% · $39.0k
268 / 218.5 h
26-1043 PRJ-2026-403 Nyrstar Port Pirie Conveyor gantry & support steel — Port Pirie
PM Craig Pearce Fabrication Contract $232,273.10 Claimed 30% $69,681.94
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Gantry structural steel — UB/UC + bracing $160,677.95 69.2% 30% · $48.2k NYR-PP-23019
919 / 213.9 h
12 Oct
2 Walkway, handrail & kickplate to gantry $71,595.15 30.8% 30% · $21.5k NYR-PP-23019
407 / 140.9 h
12 Oct
Project total (2 items) $232,273.10100% 30% · $69.7k
1326 / 354.8 h
26-1042 PRJ-2026-402 Century Engineering Access platform & caged ladder — plant upgrade
PM Craig Pearce Site Install Contract $39,429.60 Claimed 87% $34,228.88
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Access platform 3.6 x 2.4m — grating & handrail $26,003.65 65.9% 80% · $20.8k CE-11872
148 / 133.9 h
12 Oct
2 Caged ladder 5.2m with landing $13,425.95 34.1% 100% · $13.4k CE-11872
73 / 70 h
07 Sep
Project total (2 items) $39,429.60100% 87% · $34.2k
221 / 203.9 h
26-1041 PRJ-2026-401 Badge Constructions Louvre screens & sunhoods — airport carpark facade
PM Craig Pearce Fabrication Contract $140,235.95 Claimed 46% $64,706.98
ItemDescriptionStatusValue% contract ClaimedClient POAllowed / actual hrsDue w/c
1 Aluminium louvre screen frames & blades — Type A $48,680.50 34.7% 30% · $14.6k BC-24-1187
274 / 128.8 h
12 Oct
2 Perimeter sunhoods & flashings — folded sheet $38,148.25 27.2% 50% · $19.1k BC-24-1187
214 / 126.1 h
19 Oct
3 Louvre screens — Type B to stair core $21,297.25 15.2% 10% · $2.1k BC-24-1187
122 / 5 h
19 Oct
4 Site install, access & fixings $32,109.95 22.9% 90% · $28.9k BC-24-1187
183 / 171.7 h
26 Oct
Project total (4 items) $140,235.95100% 46% · $64.7k
793 / 431.6 h
Completed projects stay in the register for history and reporting.