26-1060 · PRJ-2026-412

Access platforms & walkways — WWTP
Demo 05 Oct 2026
← Register
26-1060 PRJ-2026-412 Complete Complete MYOB

Access platforms & walkways — WWTP

Client Flinders Ports Site Port Adelaide SA PM Craig Pearce Client PO FP-77341 Programme 03 Sep 2026 → 26 Sep 2026 Quote Q-2026-1060
Progress100%
Contract value (ex GST)
$49.2k
2 items
Claimed to date
$49.2k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
29.8%
from quote-book costings
Allowed / actual hours
274 / 268
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Stair & landings — access platforms & walkways $24,325.90 49.4% 100% · $24.3k FP-77341
72 / 74
46 / 44
19 / 18
21 Sep —
2 Screens — access platforms & walkways $24,883.90 50.6% 100% · $24.9k FP-77341
72 / 72
46 / 42
19 / 18
21 Sep —
Progress claims$49,209.80 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4240 50% 13 Sep 2026 $27,065.39 MYOB Pushed to MYOB Paid
#2 · INV-2026-4241 50% 20 Sep 2026 $27,065.39 MYOB Pushed to MYOB Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders4 · $11,704.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7156 Southern Steel Group 1 12 Sep 2026 $4,712.00 Received
PO-2026-7157 Coventry Fasteners 1 07 Sep 2026 $1,176.00 Received
PO-2026-7158 Vulcan Steel 2 06 Sep 2026 $4,640.00 Received
PO-2026-7159 Coventry Fasteners 2 05 Sep 2026 $1,176.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
11 Sep 2026 Yang Li 1 Office 8
11 Sep 2026 Ryan Tsoukalas 1 Factory 8
11 Sep 2026 Anthony Reid 2 Factory 8
11 Sep 2026 Kyle Mancini 1 Site 8
11 Sep 2026 Tyler Hocking 2 Site 8
10 Sep 2026 Sam Nguyen 1 Office 8
10 Sep 2026 Yang Li 2 Office 2
10 Sep 2026 Mitch Daly 1 Factory 8
10 Sep 2026 Dean Roberts 1 Factory 2
10 Sep 2026 Josh Kerr 2 Factory 8
10 Sep 2026 Dean Roberts 2 Factory 8
09 Sep 2026 Yang Li 2 Office 8
09 Sep 2026 Anthony Reid 1 Factory 8
09 Sep 2026 Dean Roberts 1 Factory 8
09 Sep 2026 Ryan Tsoukalas 2 Factory 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Flinders Ports. Compliance →
SharePointSynced
Co-Create › Projects › 26-1060 Flinders Ports — Access platforms & walkways — WWTP
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Flinders Ports
Grant Tregoning · grant@flindersports.com.au
Port Adelaide SA · NET 30