Co-Create

26-1071 · PRJ-2026-420

Grandstand balustrade & rails
Demo 05 Oct 2026
← Register
26-1071 PRJ-2026-420 Complete Complete MYOB

Grandstand balustrade & rails

Client Flinders Ports Site Port Adelaide SA PM Matthew Warren Client PO FP-77341 Programme 03 Jul 2026 → 26 Jul 2026 Quote Q-2026-1071
Progress100%
Contract value (ex GST)
$225.7k
2 items
Claimed to date
$225.7k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
30.2%
from quote-book costings
Allowed / actual hours
1290 / 1321
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Access platform — grandstand balustrade & rails $112,831.95 50% 100% · $112.8k FP-77341
344 / 357
223 / 224
78 / 71
20 Jul —
2 Stair & landings — grandstand balustrade & rails $112,846.90 50% 100% · $112.8k FP-77341
344 / 358
223 / 230
78 / 81
20 Jul —
Progress claims$225,678.86 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4258 50% 13 Jul 2026 $124,123.37 MYOB Pushed to MYOB Paid
#2 · INV-2026-4259 50% 20 Jul 2026 $124,123.37 MYOB Pushed to MYOB Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders4 · $56,416.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7201 Coventry Fasteners 2 10 Jul 2026 $5,640.00 Received
PO-2026-7200 Vulcan Steel 2 07 Jul 2026 $22,568.00 Received
PO-2026-7198 Vulcan Steel 1 07 Jul 2026 $22,568.00 Received
PO-2026-7199 Coventry Fasteners 1 05 Jul 2026 $5,640.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
24 Jul 2026 Yang Li 2 Office 8
24 Jul 2026 Peter Voulgaris 1 Factory 8
24 Jul 2026 Dean Roberts 1 Factory 8
24 Jul 2026 Mitch Daly 1 Factory 8
24 Jul 2026 Josh Kerr 2 Factory 8
24 Jul 2026 Anthony Reid 2 Factory 8
24 Jul 2026 Josh Kerr 2 Factory 8
24 Jul 2026 Ben Hartley 1 Site 8
24 Jul 2026 Luke Bianco 2 Site 8
24 Jul 2026 Tyler Hocking 2 Site 8
23 Jul 2026 Yang Li 2 Office 8
23 Jul 2026 Mitch Daly 1 Factory 8
23 Jul 2026 Ryan Tsoukalas 1 Factory 8
23 Jul 2026 Josh Kerr 1 Factory 8
23 Jul 2026 Peter Voulgaris 2 Factory 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Flinders Ports. Compliance →
SharePointSynced
Co-Create › Projects › 26-1071 Flinders Ports — Grandstand balustrade & rails
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Flinders Ports
Grant Tregoning · grant@flindersports.com.au
Port Adelaide SA · NET 30