Co-Create

Item 1 — Q-2026-1041

Quote book · Badge Constructions — Louvre screens & sunhoods — airport carpark facade
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1041· Job 26-1041· Badge Constructions· Estimator Tanya Fielke· Valid to 28 Sep 2026
‹ 1 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$11,949.00 Sell$14,936.25
DescriptionQtyUnitUnit costMargin CostSell
$
%
$9,570.00 $11,962.50
$
%
$2,379.00 $2,973.75
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours145 Cost$8,410.00 Sell$13,876.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$8,410.00 $13,876.50
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours94 Cost$6,016.00 Sell$9,926.40
DescriptionQtyUnitUnit costMargin CostSell
$
%
$6,016.00 $9,926.40
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$4,309.00 Sell$4,955.35
DescriptionQtyUnitUnit costMargin CostSell
$
%
$2,370.00 $2,725.50
$
%
$1,939.00 $2,229.85
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours35 Cost$3,420.00 Sell$4,986.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$1,584.00 $2,455.20
$
%
$648.00 $1,004.40
$
%
$900.00 $1,080.00
No allowances on this item.