Item 4 — Q-2026-1041

Quote book · Badge Constructions — Louvre screens & sunhoods — airport carpark facade
Demo 05 Oct 2026
← Back to quote
Item4
Q-2026-1041· Job 26-1041· Badge Constructions· Estimator Tanya Fielke· Valid to 28 Sep 2026
‹ 4 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$7,899.00 Sell$9,873.75
DescriptionQtyUnitUnit costMargin CostSell
$
%
$6,325.00 $7,906.25
$
%
$1,574.00 $1,967.50
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours96 Cost$5,568.00 Sell$9,187.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$5,568.00 $9,187.20
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours62 Cost$3,968.00 Sell$6,547.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,968.00 $6,547.20
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$2,852.00 Sell$3,279.80
DescriptionQtyUnitUnit costMargin CostSell
$
%
$2,852.00 $3,279.80
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours25 Cost$2,160.00 Sell$3,222.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$1,080.00 $1,674.00
$
%
$432.00 $669.60
$
%
$360.00 $432.00
No allowances on this item.