Item2
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$6,738.00 Sell$8,422.50
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $5,394.00 | $6,742.50 | ||||
$ | % | $1,344.00 | $1,680.00 | ||||
| No materials on this item — add a row below. | |||||||
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours82 Cost$4,756.00 Sell$7,847.40
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $4,756.00 | $7,847.40 | ||||
| No fabrication on this item — add a row below. | |||||||
3
Installation
Site hours × rate — becomes the site allowance
Hours53 Cost$3,392.00 Sell$5,596.80
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $3,392.00 | $5,596.80 | ||||
| No installation on this item — add a row below. | |||||||
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$2,435.00 Sell$2,800.25
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $2,435.00 | $2,800.25 | ||||
| No contract services on this item — add a row below. | |||||||
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours22 Cost$2,304.00 Sell$3,319.20
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $288.00 | $446.40 | ||||
$ | % | $936.00 | $1,450.80 | ||||
$ | % | $360.00 | $558.00 | ||||
$ | % | $720.00 | $864.00 | ||||
| No allowances on this item — add a row below. | |||||||