Co-Create

Item 1 — Q-2026-1056

Quote book · Hansen Yuncken — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1056· Job 26-1056· Hansen Yuncken· Estimator Matthew Warren· Valid to 16 Sep 2026
‹ 1 of 7 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$23,490.00 Sell$29,362.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$18,786.00 $23,482.50
$
%
$4,704.00 $5,880.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours287 Cost$16,646.00 Sell$27,465.90
DescriptionQtyUnitUnit costMargin CostSell
$
%
$16,646.00 $27,465.90
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours186 Cost$11,904.00 Sell$19,641.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$11,904.00 $19,641.60
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$8,513.00 Sell$9,789.95
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,400.00 $3,910.00
$
%
$5,113.00 $5,879.95
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours66 Cost$5,652.00 Sell$8,445.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$3,168.00 $4,910.40
$
%
$1,296.00 $2,008.80
$
%
$900.00 $1,080.00
No allowances on this item.