Co-Create

Item 5 — Q-2026-1056

Quote book · Hansen Yuncken — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
Demo 05 Oct 2026
← Back to quote
Item5
Q-2026-1056· Job 26-1056· Hansen Yuncken· Estimator Matthew Warren· Valid to 16 Sep 2026
‹ 5 of 7 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$17,762.00 Sell$22,202.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$14,210.00 $17,762.50
$
%
$3,552.00 $4,440.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours217 Cost$12,586.00 Sell$20,766.90
DescriptionQtyUnitUnit costMargin CostSell
$
%
$12,586.00 $20,766.90
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours140 Cost$8,960.00 Sell$14,784.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$8,960.00 $14,784.00
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$6,435.00 Sell$7,400.25
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,539.00 $4,069.85
$
%
$2,896.00 $3,330.40
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours50 Cost$4,140.00 Sell$6,228.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,376.00 $3,682.80
$
%
$936.00 $1,450.80
$
%
$540.00 $648.00
No allowances on this item.