Item 2 — Q-2026-1057

Quote book · Mossop Construction + Interiors — Feature stair & balustrades — Kent Town apartments
Demo 05 Oct 2026
← Back to quote
Item2
Q-2026-1057· Job 26-1057· Mossop Construction + Interiors· Estimator Tanya Fielke· Valid to 08 Oct 2026
‹ 2 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$15,357.00 Sell$19,196.25
DescriptionQtyUnitUnit costMargin CostSell
$
%
$12,285.00 $15,356.25
$
%
$3,072.00 $3,840.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours187 Cost$10,846.00 Sell$17,895.90
DescriptionQtyUnitUnit costMargin CostSell
$
%
$10,846.00 $17,895.90
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours121 Cost$7,744.00 Sell$12,777.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$7,744.00 $12,777.60
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$5,539.00 Sell$6,369.85
DescriptionQtyUnitUnit costMargin CostSell
$
%
$2,200.00 $2,530.00
$
%
$3,339.00 $3,839.85
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours44 Cost$3,528.00 Sell$5,342.40
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,088.00 $3,236.40
$
%
$792.00 $1,227.60
$
%
$360.00 $432.00
No allowances on this item.