Co-Create

Item 4 — Q-2026-1064

Quote book · Hansen Yuncken — Conveyor support steel
Demo 05 Oct 2026
← Back to quote
Item4
Q-2026-1064· Job 26-1064· Hansen Yuncken· Estimator Matthew Warren· Valid to 03 Sep 2026
‹ 4 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$6,348.00 Sell$7,935.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$5,088.00 $6,360.00
$
%
$1,260.00 $1,575.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours77 Cost$4,466.00 Sell$7,368.90
DescriptionQtyUnitUnit costMargin CostSell
$
%
$4,466.00 $7,368.90
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours50 Cost$3,200.00 Sell$5,280.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,200.00 $5,280.00
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$2,282.00 Sell$2,624.30
DescriptionQtyUnitUnit costMargin CostSell
$
%
$1,255.00 $1,443.25
$
%
$1,027.00 $1,181.05
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours21 Cost$1,872.00 Sell$2,775.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$864.00 $1,339.20
$
%
$360.00 $558.00
$
%
$360.00 $432.00
No allowances on this item.