Item2
Q-2026-1068· Job 26-1068· Detmold Group· Estimator Matthew Warren· Valid to 07 Aug 2026
‹ 2 of 2 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$9,843.00 Sell$12,303.75
DescriptionQtyUnitUnit costMargin CostSell
$
%
$7,875.00 $9,843.75
$
%
$1,968.00 $2,460.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours120 Cost$6,960.00 Sell$11,484.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$6,960.00 $11,484.00
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours78 Cost$4,992.00 Sell$8,236.80
DescriptionQtyUnitUnit costMargin CostSell
$
%
$4,992.00 $8,236.80
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$3,539.00 Sell$4,069.85
DescriptionQtyUnitUnit costMargin CostSell
$
%
$1,400.00 $1,610.00
$
%
$2,139.00 $2,459.85
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours29 Cost$2,448.00 Sell$3,668.40
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$1,296.00 $2,008.80
$
%
$504.00 $781.20
$
%
$360.00 $432.00