Item2
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$29,526.00 Sell$36,907.50
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $23,622.00 | $29,527.50 | ||||
$ | % | $5,904.00 | $7,380.00 | ||||
| No materials on this item. | |||||||
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours360 Cost$20,880.00 Sell$34,452.00
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $20,880.00 | $34,452.00 | ||||
| No fabrication on this item. | |||||||
3
Installation
Site hours × rate — becomes the site allowance
Hours233 Cost$14,912.00 Sell$24,604.80
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $14,912.00 | $24,604.80 | ||||
| No installation on this item. | |||||||
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$10,696.00 Sell$12,300.40
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $10,696.00 | $12,300.40 | ||||
| No contract services on this item. | |||||||
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours81 Cost$6,732.00 Sell$10,119.60
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $288.00 | $446.40 | ||||
$ | % | $3,960.00 | $6,138.00 | ||||
$ | % | $1,584.00 | $2,455.20 | ||||
$ | % | $900.00 | $1,080.00 | ||||
| No allowances on this item. | |||||||