Co-Create

Item 4 — Q-2026-1078

Quote book · Seeley International — Structural steel & stair — warehouse extension
Demo 05 Oct 2026
← Back to quote
Item4
Q-2026-1078· Job 26-1078· Seeley International· Estimator Matthew Warren· Valid to 14 Jun 2026
‹ 4 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$20,508.00 Sell$25,635.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$16,416.00 $20,520.00
$
%
$4,092.00 $5,115.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours249 Cost$14,442.00 Sell$23,829.30
DescriptionQtyUnitUnit costMargin CostSell
$
%
$14,442.00 $23,829.30
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours161 Cost$10,304.00 Sell$17,001.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$10,304.00 $17,001.60
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$7,448.00 Sell$8,565.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,000.00 $3,450.00
$
%
$4,448.00 $5,115.20
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours57 Cost$5,004.00 Sell$7,441.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,736.00 $4,240.80
$
%
$1,080.00 $1,674.00
$
%
$900.00 $1,080.00
No allowances on this item.