Co-Create

Item 1 — Q-2026-1081

Quote book · Century Engineering — Louvre screens & architectural mesh
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1081· Job 26-1081· Century Engineering· Estimator Tanya Fielke· Valid to 02 Jun 2026
‹ 1 of 2 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$21,937.00 Sell$27,421.25
DescriptionQtyUnitUnit costMargin CostSell
$
%
$17,545.00 $21,931.25
$
%
$4,392.00 $5,490.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours268 Cost$15,544.00 Sell$25,647.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$15,544.00 $25,647.60
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours173 Cost$11,072.00 Sell$18,268.80
DescriptionQtyUnitUnit costMargin CostSell
$
%
$11,072.00 $18,268.80
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$7,974.00 Sell$9,170.10
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,200.00 $3,680.00
$
%
$4,774.00 $5,490.10
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours61 Cost$5,112.00 Sell$7,671.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,952.00 $4,575.60
$
%
$1,152.00 $1,785.60
$
%
$720.00 $864.00
No allowances on this item.