1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$11,053.00 Sell$13,816.25
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $8,845.00 | $11,056.25 | ||||
$ | % | $2,208.00 | $2,760.00 | ||||
| No materials on this item — add a row below. | |||||||
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours135 Cost$7,830.00 Sell$12,919.50
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $7,830.00 | $12,919.50 | ||||
| No fabrication on this item — add a row below. | |||||||
3
Installation
Site hours × rate — becomes the site allowance
Hours87 Cost$5,568.00 Sell$9,187.20
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $5,568.00 | $9,187.20 | ||||
| No installation on this item — add a row below. | |||||||
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$4,000.00 Sell$4,600.00
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $2,200.00 | $2,530.00 | ||||
$ | % | $1,800.00 | $2,070.00 | ||||
| No contract services on this item — add a row below. | |||||||
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours33 Cost$3,456.00 Sell$4,978.80
| Description | Qty | Unit | Unit cost | Margin | Cost | Sell | |
|---|---|---|---|---|---|---|---|
$ | % | $288.00 | $446.40 | ||||
$ | % | $1,512.00 | $2,343.60 | ||||
$ | % | $576.00 | $892.80 | ||||
$ | % | $1,080.00 | $1,296.00 | ||||
| No allowances on this item — add a row below. | |||||||