Co-Create

Item 1 — Q-2026-1049

Quote book · City of Onkaparinga — Grandstand balustrade & handrails — sporting club
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1049· Job 26-1049· City of Onkaparinga· Estimator Tanya Fielke· Valid to 27 Oct 2026
‹ 1 of 2 ›
Pending
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$4,566.00 Sell$5,707.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,654.00 $4,567.50
$
%
$912.00 $1,140.00
No materials on this item — add a row below.
New rows: m · 25% margin
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours56 Cost$3,248.00 Sell$5,359.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,248.00 $5,359.20
No fabrication on this item — add a row below.
New rows: hr @ $58.00 · 65% margin
3
Installation
Site hours × rate — becomes the site allowance
Hours36 Cost$2,304.00 Sell$3,801.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$2,304.00 $3,801.60
No installation on this item — add a row below.
New rows: hr @ $64.00 · 65% margin
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$1,691.00 Sell$1,944.65
DescriptionQtyUnitUnit costMargin CostSell
$
%
$700.00 $805.00
$
%
$991.00 $1,139.65
No contract services on this item — add a row below.
New rows: ea · 15% margin
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours16 Cost$1,872.00 Sell$2,649.60
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$648.00 $1,004.40
$
%
$216.00 $334.80
$
%
$720.00 $864.00
No allowances on this item — add a row below.
New rows: hr @ $72.00 · 55% margin