Job Card JC-2026-3060

Item 2 — Grab rails & wall-mounted rails (DDA)
Demo 05 Oct 2026
Stage
Fabrication
ITP progress
4 / 8
hold points 2 / 4 signed
Job value
$11,919.65
Due
19 Oct 2026
High
Workshop route
✓ Queued
✓ Cutting
● Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-404 · Sarah Constructions
Quantity1
MaterialAluminium
FinishHot-dip galvanised
Assigned toAnthony Reid
Due date19 Oct 2026
Heat / traceability no.minted on completion
ProjectPRJ-2026-404 · Item 2
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
4 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
20 Sep 2026 · 10:40
2
Material certificates / heat numbers recorded
Passed
Dean Roberts
20 Sep 2026 · 14:30
3
Cut list & set-out checked
Passed
Anthony Reid
22 Sep 2026 · 08:15
4
Fit-up inspection before welding
HOLD POINT
Passed
Yang Li
28 Sep 2026 · 13:05
5
Weld visual inspection to AS/NZS 1554.1
Pending —
6
Dimensional check against drawing
Pending —
7
Surface prep & coating inspection
HOLD POINT
Pending —
8
Final release to site
HOLD POINT
Pending —
Customer
Sarah Constructions
Marleston SA
Project
PRJ-2026-404 · Job 26-1044
Project item
Item 2 — Grab rails & wall-mounted rails (DDA)
PRJ-2026-404 · register status Factory
Allowed vs actual hours
Factory27.5 h / 32 h 86%
Site0 h / 21 h 0%
Office9 h / 11 h 82%
Labour & time →
Recent time on this item
Mitch Daly
22 Sep · Factory · 11:00–15:11
3.7 h
Ryan Tsoukalas
22 Sep · Factory · 06:32–10:30
4 h
Josh Kerr
22 Sep · Factory · 06:30–10:30
4 h
Yang Li
21 Sep · Office · 08:00–12:00
4 h
Ryan Tsoukalas
17 Sep · Factory · 11:00–15:11
3.7 h
Anthony Reid
16 Sep · Factory · 11:00–15:44
4.2 h
Peter Voulgaris
15 Sep · Factory · 06:32–10:30
4 h
Josh Kerr
14 Sep · Factory · 11:00–15:30
4 h
Sam Nguyen
25 Aug · Office · 08:00–13:30
5 h