26-1044 PRJ-2026-404 Finishing PayApps
Stainless handrail & grab-rail package — hospital
Client Sarah Constructions Site Marleston SA PM Craig Pearce Client PO SC-PO-30552 Programme 24 Aug 2026 → 19 Oct 2026 Quote Q-2026-1044
Progress66%
Contract value (ex GST)
$48.6k
3 items
Claimed to date
$39.0k
80% of contract
Scheduled claims (draft)
$9.6k
1 staged · PayApps
Gross profit (items)
29.6%
from quote-book costings
Allowed / actual hours
268 / 218.5
factory · site · office
Progress claims$39,000.15 claimed · $9,630.96 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4213 | 27% | 05 Sep 2026 | $14,300.06 | PayApps | Lodged in PayApps | Paid |
| #2 · INV-2026-4214 | 27% | 18 Sep 2026 | $14,300.06 | PayApps | Lodged in PayApps | Paid |
| #3 · INV-2026-4215 | 27% | 01 Oct 2026 | $14,300.06 | PayApps | Lodged in PayApps | Sent |
| #4 · INV-2026-4216 | 20% | 20 Oct 2026 | $10,594.06 | PayApps | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Site access & crane booking discussed. SWMS accepted by client.
Actions Tyler — book EWP for Thursday · Craig — chase galvaniser ETA
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Sam — issue rev C drawings by Wed · Craig — chase galvaniser ETA
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Hours tracking vs allowance reviewed item by item.
Actions Sam — issue rev C drawings by Wed · Tyler — book EWP for Thursday
Purchase orders6 · $11,176.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7115 | Southern Steel Group | 1 | 01 Oct 2026 | $5,616.00 | Received |
| PO-2026-7117 | Vulcan Steel | 2 | 25 Sep 2026 | $2,079.00 | Sent |
| PO-2026-7118 | Coventry Fasteners | 2 | 24 Sep 2026 | $520.00 | Sent |
| PO-2026-7119 | InfraBuild Steel Centre | 3 | 23 Sep 2026 | $1,248.00 | Received |
| PO-2026-7120 | Coventry Fasteners | 3 | 21 Sep 2026 | $309.00 | Received |
| PO-2026-7116 | Coventry Fasteners | 1 | 19 Sep 2026 | $1,404.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 02 Oct 2026 | Luke Bianco | 1 | Site | 8.4 |
| 01 Oct 2026 | Luke Bianco | 1 | Site | 8.4 |
| 30 Sep 2026 | Tyler Hocking | 1 | Site | 7.9 |
| 29 Sep 2026 | Kyle Mancini | 1 | Site | 8.5 |
| 24 Sep 2026 | Kyle Mancini | 1 | Site | 8.4 |
| 22 Sep 2026 | Mitch Daly | 2 | Factory | 3.7 |
| 22 Sep 2026 | Ryan Tsoukalas | 2 | Factory | 4 |
| 22 Sep 2026 | Josh Kerr | 2 | Factory | 4 |
| 21 Sep 2026 | Yang Li | 2 | Office | 4 |
| 17 Sep 2026 | Ryan Tsoukalas | 2 | Factory | 3.7 |
| 17 Sep 2026 | Tyler Hocking | 3 | Site | 8.5 |
| 17 Sep 2026 | Luke Bianco | 1 | Site | 7.9 |
| 16 Sep 2026 | Anthony Reid | 2 | Factory | 4.2 |
| 15 Sep 2026 | Peter Voulgaris | 2 | Factory | 4 |
| 14 Sep 2026 | Josh Kerr | 2 | Factory | 4 |
Crew assigned
w/c 05 Oct38 h
Josh Kerr· 238h
w/c 12 Oct76 h
Ben Hartley· 138hTyler Hocking· 138h
w/c 19 Oct114 h
Ben Hartley· 138hLuke Bianco· 138hTyler Hocking· 138h
w/c 26 Oct38 h
Dean Roberts· 238h
SWMSAccepted
CMP-1016 SWMS — Stainless handrail & grab-rail package — hospital Accepted
Prepared in JSEasy · submitted to and accepted by Sarah Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1044 Sarah Constructions — Stainless handrail & grab-rail package — hospital
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client