Co-Create

26-1044 · PRJ-2026-404

Stainless handrail & grab-rail package — hospital
Demo 05 Oct 2026
← Register
26-1044 PRJ-2026-404 Finishing PayApps

Stainless handrail & grab-rail package — hospital

Client Sarah Constructions Site Marleston SA PM Craig Pearce Client PO SC-PO-30552 Programme 24 Aug 2026 → 19 Oct 2026 Quote Q-2026-1044
Progress66%
Contract value (ex GST)
$48.6k
3 items
Claimed to date
$39.0k
80% of contract
Scheduled claims (draft)
$9.6k
1 staged · PayApps
Gross profit (items)
29.6%
from quote-book costings
Allowed / actual hours
268 / 218.5
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 316 stainless handrail to stairs — satin finish $28,840.85 59.3% 90% · $26.0k SC-PO-30552
86 / 78
55 / 49.5
22 / 20
12 Oct JC-2026-3059
ITP 8/8
2 Grab rails & wall-mounted rails (DDA) $11,919.65 24.5% 50% · $6.0k SC-PO-30552
32 / 27.5
21 / 0
11 / 9
19 Oct JC-2026-3060
ITP 4/8
3 Stainless mesh infill panels $7,870.60 16.2% 90% · $7.1k SC-PO-30552
19 / 17
12 / 8.5
10 / 9
19 Oct JC-2026-3061
ITP 8/8
Progress claims$39,000.15 claimed · $9,630.96 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4213 27% 05 Sep 2026 $14,300.06 PayApps Lodged in PayApps Paid
#2 · INV-2026-4214 27% 18 Sep 2026 $14,300.06 PayApps Lodged in PayApps Paid
#3 · INV-2026-4215 27% 01 Oct 2026 $14,300.06 PayApps Lodged in PayApps Sent
#4 · INV-2026-4216 20% 20 Oct 2026 $10,594.06 PayApps Draft Draft
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Site access & crane booking discussed. SWMS accepted by client.
Actions Tyler — book EWP for Thursday · Craig — chase galvaniser ETA
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Sam — issue rev C drawings by Wed · Craig — chase galvaniser ETA
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Hours tracking vs allowance reviewed item by item.
Actions Sam — issue rev C drawings by Wed · Tyler — book EWP for Thursday
Purchase orders6 · $11,176.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7115 Southern Steel Group 1 01 Oct 2026 $5,616.00 Received
PO-2026-7117 Vulcan Steel 2 25 Sep 2026 $2,079.00 Sent
PO-2026-7118 Coventry Fasteners 2 24 Sep 2026 $520.00 Sent
PO-2026-7119 InfraBuild Steel Centre 3 23 Sep 2026 $1,248.00 Received
PO-2026-7120 Coventry Fasteners 3 21 Sep 2026 $309.00 Received
PO-2026-7116 Coventry Fasteners 1 19 Sep 2026 $1,404.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
02 Oct 2026 Luke Bianco 1 Site 8.4
01 Oct 2026 Luke Bianco 1 Site 8.4
30 Sep 2026 Tyler Hocking 1 Site 7.9
29 Sep 2026 Kyle Mancini 1 Site 8.5
24 Sep 2026 Kyle Mancini 1 Site 8.4
22 Sep 2026 Mitch Daly 2 Factory 3.7
22 Sep 2026 Ryan Tsoukalas 2 Factory 4
22 Sep 2026 Josh Kerr 2 Factory 4
21 Sep 2026 Yang Li 2 Office 4
17 Sep 2026 Ryan Tsoukalas 2 Factory 3.7
17 Sep 2026 Tyler Hocking 3 Site 8.5
17 Sep 2026 Luke Bianco 1 Site 7.9
16 Sep 2026 Anthony Reid 2 Factory 4.2
15 Sep 2026 Peter Voulgaris 2 Factory 4
14 Sep 2026 Josh Kerr 2 Factory 4
Crew assigned
w/c 05 Oct38 h
Josh Kerr· 238h
w/c 12 Oct76 h
Ben Hartley· 138hTyler Hocking· 138h
w/c 19 Oct114 h
Ben Hartley· 138hLuke Bianco· 138hTyler Hocking· 138h
w/c 26 Oct38 h
Dean Roberts· 238h
Open the shift schedule →
SWMSAccepted
CMP-1016 SWMS — Stainless handrail & grab-rail package — hospital Accepted
Prepared in JSEasy · submitted to and accepted by Sarah Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1044 Sarah Constructions — Stainless handrail & grab-rail package — hospital
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Sarah Constructions
David Petrusma · david@sarahconstruct.com.au
Marleston SA · NET 30