Stage
Complete
ITP progress
8 / 8
hold points 4 / 4 signed
Job value
$7,870.60
Due
19 Oct 2026
Urgent
Workshop route
✓ Queued
✓ Cutting
✓ Fabrication
✓ Welding
✓ Finishing
● Complete
Complete — heat number minted
Details
PRJ-2026-404 · Sarah Constructions
| Quantity | 1 |
| Material | Galvanised |
| Finish | Hot-dip galvanised |
| Assigned to | Mitch Daly |
| Due date | 19 Oct 2026 |
| Heat / traceability no. | HT-40407 |
| Project | PRJ-2026-404 · Item 3 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
8 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 04 Oct 2026 · 13:05 | |
| 2 | Material certificates / heat numbers recorded | Passed | Anthony Reid 29 Sep 2026 · 14:30 | |
| 3 | Cut list & set-out checked | Passed | Anthony Reid 24 Sep 2026 · 10:40 | |
| 4 | Fit-up inspection before welding HOLD POINT | Passed | Yang Li 03 Oct 2026 · 14:30 | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Passed | Anthony Reid 22 Sep 2026 · 10:40 | |
| 6 | Dimensional check against drawing | Passed | Anthony Reid 27 Sep 2026 · 10:40 | |
| 7 | Surface prep & coating inspection HOLD POINT | Passed | Yang Li 17 Sep 2026 · 13:05 | |
| 8 | Final release to site HOLD POINT | Passed | Yang Li 21 Sep 2026 · 10:40 |
Project item
Item 3 — Stainless mesh infill panels
PRJ-2026-404 · register status Site
Allowed vs actual hours
Factory17 h / 19 h 89%
Site8.5 h / 12 h 70%
Office9 h / 10 h 90%
Recent time on this item
17 Sep · Site · 06:10–15:07
8.5 h
28 Aug · Factory · 06:30–07:30
1 h
27 Aug · Office · 08:00–09:00
1 h
27 Aug · Factory · 06:30–15:00
8 h
26 Aug · Office · 08:00–16:30
8 h
26 Aug · Factory · 06:30–15:00
8 h