Co-Create

Job Card JC-2026-3062

Item 1 — Galvanised balustrade to AS 1657 — 64m
Demo 05 Oct 2026
Stage
Queued
ITP progress
1 / 8
hold points 1 / 4 signed
Job value
$13,954.85
Due
13 Oct 2026
High
Workshop route
● Queued
Cutting
Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-405 · SA Water
Quantity1
MaterialMild Steel
FinishGalvanised + 2-pack
Assigned toJosh Kerr
Due date13 Oct 2026
Heat / traceability no.minted on completion
ProjectPRJ-2026-405 · Item 1
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
1 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
16 Sep 2026 · 14:30
2
Material certificates / heat numbers recorded
Pending —
3
Cut list & set-out checked
Pending —
4
Fit-up inspection before welding
HOLD POINT
Pending —
5
Weld visual inspection to AS/NZS 1554.1
Pending —
6
Dimensional check against drawing
Pending —
7
Surface prep & coating inspection
HOLD POINT
Pending —
8
Final release to site
HOLD POINT
Pending —
Customer
SA Water
Adelaide SA
Project
PRJ-2026-405 · Job 26-1045
Project item
Item 1 — Galvanised balustrade to AS 1657 — 64m
PRJ-2026-405 · register status Office
Allowed vs actual hours
Factory0 h / 39 h 0%
Site0 h / 25 h 0%
Office4 h / 12 h 33%
Labour & time →
Recent time on this item
Sam Nguyen
23 Sep · Office · 08:00–12:00
4 h