Co-Create

26-1045 · PRJ-2026-405

Balustrade & FRP walkway — pump station upgrade
Demo 05 Oct 2026
← Register
26-1045 PRJ-2026-405 Detailing MYOB

Balustrade & FRP walkway — pump station upgrade

Client SA Water Site Adelaide SA PM Craig Pearce Client PO SAW-4500912 Programme 25 Sep 2026 → 26 Nov 2026 Quote Q-2026-1045
Progress10%
Contract value (ex GST)
$74.4k
3 items
Claimed to date
$7.9k
11% of contract
Scheduled claims (draft)
$66.4k
1 staged · MYOB
Gross profit (items)
28.7%
from quote-book costings
Allowed / actual hours
367 / 8
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Galvanised balustrade to AS 1657 — 64m $13,954.85 18.8% 0% · $0 SAW-4500912
39 / 0
25 / 0
12 / 4
12 Oct JC-2026-3062
ITP 1/8
2 Access walkway with FRP grating & kickplate $51,016.15 68.6% 10% · $5.1k SAW-4500912
154 / 0
100 / 0
37 / 4
19 Oct JC-2026-3063
ITP 1/8
3 Loose fixings, chemsets & anchors — supply $9,400.00 12.6% 30% · $2.8k SAW-4500912
0 / 0
0 / 0
0 / 0
26 Oct —
Progress claims$7,921.62 claimed · $66,449.38 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4217 11% 02 Oct 2026 $8,713.78 MYOB Pushed to MYOB Sent
#2 · INV-2026-4218 89% 17 Oct 2026 $73,094.32 MYOB Draft Draft
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts
Hours tracking vs allowance reviewed item by item.
Actions Craig — chase galvaniser ETA · Sam — issue rev C drawings by Wed
Purchase orders5 · $23,450.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7122 Coventry Fasteners 1 01 Oct 2026 $645.00 Draft
PO-2026-7124 Coventry Fasteners 2 23 Sep 2026 $2,534.00 Sent
PO-2026-7123 InfraBuild Steel Centre 2 18 Sep 2026 $10,168.00 Sent
PO-2026-7121 Vulcan Steel 1 15 Sep 2026 $2,583.00 Draft
PO-2026-7125 Coventry Fasteners 3 14 Sep 2026 $7,520.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
02 Oct 2026 Yang Li 2 Office 4
23 Sep 2026 Sam Nguyen 1 Office 4
Crew assigned
w/c 26 Oct68 h
Anthony Reid· 338hYang Li· 330h
Open the shift schedule →
SWMSDraft
CMP-1017 SWMS — Balustrade & FRP walkway — pump station upgrade Draft
Prepared in JSEasy · submitted to and accepted by SA Water. Compliance →
SharePointSynced
Co-Create › Projects › 26-1045 SA Water — Balustrade & FRP walkway — pump station upgrade
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
SA Water
Helen Trewartha · helen@sawater.com.au
Adelaide SA · NET 45