Stage
Queued
ITP progress
1 / 8
hold points 1 / 4 signed
Job value
$51,016.15
Due
24 Oct 2026
Normal
Workshop route
● Queued
Cutting
Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-405 · SA Water
| Quantity | 1 |
| Material | Aluminium |
| Finish | Hot-dip galvanised |
| Assigned to | Josh Kerr |
| Due date | 24 Oct 2026 |
| Heat / traceability no. | minted on completion |
| Project | PRJ-2026-405 · Item 2 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
1 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 15 Sep 2026 · 10:40 | |
| 2 | Material certificates / heat numbers recorded | Pending | — | |
| 3 | Cut list & set-out checked | Pending | — | |
| 4 | Fit-up inspection before welding HOLD POINT | Pending | — | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Pending | — | |
| 6 | Dimensional check against drawing | Pending | — | |
| 7 | Surface prep & coating inspection HOLD POINT | Pending | — | |
| 8 | Final release to site HOLD POINT | Pending | — |
Project item
Item 2 — Access walkway with FRP grating & kickplate
PRJ-2026-405 · register status Office
Allowed vs actual hours
Factory0 h / 154 h 0%
Site0 h / 100 h 0%
Office4 h / 37 h 11%
Recent time on this item
02 Oct · Office · 08:00–12:00
4 h