Co-Create

Job Card JC-2026-3064

Item 1 — Marine-grade access platform & landings — galv
Demo 05 Oct 2026
Stage
Complete
ITP progress
8 / 8
hold points 4 / 4 signed
Job value
$161,305.95
Due
12 Oct 2026
High
Workshop route
✓ Queued
✓ Cutting
✓ Fabrication
✓ Welding
✓ Finishing
● Complete
Complete — heat number minted
Details
PRJ-2026-406 · Flinders Ports
Quantity1
MaterialGalvanised
FinishPowder coat — Surfmist
Assigned toDean Roberts
Due date12 Oct 2026
Heat / traceability no.HT-40518
ProjectPRJ-2026-406 · Item 1
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
8 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
15 Sep 2026 · 13:05
2
Material certificates / heat numbers recorded
Passed
Anthony Reid
18 Sep 2026 · 08:15
3
Cut list & set-out checked
Passed
Anthony Reid
04 Oct 2026 · 10:40
4
Fit-up inspection before welding
HOLD POINT
Passed
Yang Li
18 Sep 2026 · 08:15
5
Weld visual inspection to AS/NZS 1554.1
Passed
Dean Roberts
18 Sep 2026 · 14:30
6
Dimensional check against drawing
Passed
Dean Roberts
28 Sep 2026 · 10:40
7
Surface prep & coating inspection
HOLD POINT
Passed
Yang Li
17 Sep 2026 · 10:40
8
Final release to site
HOLD POINT
Passed
Yang Li
27 Sep 2026 · 14:30
Customer
Flinders Ports
Port Adelaide SA
Project
PRJ-2026-406 · Job 26-1053
Project item
Item 1 — Marine-grade access platform & landings — galv
PRJ-2026-406 · register status Site
Allowed vs actual hours
Factory466 h / 492 h 95%
Site112.8 h / 318 h 35%
Office98 h / 109 h 90%
Labour & time →
Recent time on this item
Ben Hartley
24 Sep · Site · 06:01–14:41
8.2 h
Kyle Mancini
23 Sep · Site · 06:12–14:43
8 h
Luke Bianco
23 Sep · Site · 06:11–14:41
8 h
Ben Hartley
23 Sep · Site · 06:05–14:43
8.1 h
Luke Bianco
18 Sep · Site · 06:05–14:44
8.2 h
Kyle Mancini
18 Sep · Site · 06:01–14:49
8.3 h
Tyler Hocking
16 Sep · Site · 06:09–15:07
8.5 h
Ben Hartley
14 Sep · Site · 06:10–14:46
8.1 h
Josh Kerr
11 Sep · Factory · 06:30–15:00
8 h
Ryan Tsoukalas
11 Sep · Factory · 06:30–15:00
8 h
Kyle Mancini
11 Sep · Site · 06:00–14:30
8 h
Anthony Reid
10 Sep · Factory · 06:30–15:00
8 h