26-1053 PRJ-2026-406 Site Install MYOB
Berth access platform, ladders & gates — marine
Client Flinders Ports Site Port Adelaide SA PM Matthew Warren Client PO FP-77341 Programme 14 Aug 2026 → 13 Oct 2026 Quote Q-2026-1053
Progress86%
Contract value (ex GST)
$283.7k
3 items
Claimed to date
$258.7k
91% of contract
Scheduled claims (draft)
$25.0k
1 staged · MYOB
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1613 / 1338.4
factory · site · office
Progress claims$258,739.40 claimed · $24,975.02 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4219 | 23% | 26 Aug 2026 | $71,153.34 | MYOB | Pushed to MYOB | Paid |
| #2 · INV-2026-4220 | 23% | 07 Sep 2026 | $71,153.34 | MYOB | Pushed to MYOB | Paid |
| #3 · INV-2026-4221 | 23% | 19 Sep 2026 | $71,153.34 | MYOB | Pushed to MYOB | Paid |
| #4 · INV-2026-4222 | 23% | 01 Oct 2026 | $71,153.34 | MYOB | Pushed to MYOB | Sent |
| #5 · INV-2026-4223 | 9% | 20 Oct 2026 | $27,472.52 | MYOB | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Material delivery confirmed; galv turnaround on track.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Material delivery confirmed; galv turnaround on track.
Actions Sam — issue rev C drawings by Wed · Jess — lodge claim before cut-off
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Material delivery confirmed; galv turnaround on track.
Actions Craig — chase galvaniser ETA · Sam — issue rev C drawings by Wed
Purchase orders6 · $70,518.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7126 | Bianco Steel | 1 | 29 Sep 2026 | $32,240.00 | Received |
| PO-2026-7128 | InfraBuild Steel Centre | 3 | 23 Sep 2026 | $5,754.00 | Received |
| PO-2026-7129 | Coventry Fasteners | 3 | 20 Sep 2026 | $1,438.00 | Received |
| PO-2026-7127 | Coventry Fasteners | 1 | 18 Sep 2026 | $8,064.00 | Received |
| PO-2026-7134 | Vulcan Steel | 2 | 21 Aug 2026 | $18,414.00 | Received |
| PO-2026-7135 | Coventry Fasteners | 2 | 16 Aug 2026 | $4,608.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 05 Oct 2026 | Luke Bianco | 3 | Site | On now |
| 02 Oct 2026 | Tyler Hocking | 3 | Site | 8.2 |
| 28 Sep 2026 | Ben Hartley | 3 | Site | 7.8 |
| 24 Sep 2026 | Ben Hartley | 1 | Site | 8.2 |
| 23 Sep 2026 | Kyle Mancini | 1 | Site | 8 |
| 23 Sep 2026 | Luke Bianco | 1 | Site | 8 |
| 23 Sep 2026 | Tyler Hocking | 3 | Site | 8.4 |
| 23 Sep 2026 | Ben Hartley | 1 | Site | 8.1 |
| 18 Sep 2026 | Tyler Hocking | 3 | Site | 8 |
| 18 Sep 2026 | Luke Bianco | 1 | Site | 8.2 |
| 18 Sep 2026 | Kyle Mancini | 1 | Site | 8.3 |
| 16 Sep 2026 | Ben Hartley | 3 | Site | 8.3 |
| 16 Sep 2026 | Tyler Hocking | 1 | Site | 8.5 |
| 14 Sep 2026 | Ben Hartley | 1 | Site | 8.1 |
| 11 Sep 2026 | Yang Li | 2 | Office | 8 |
Crew assigned
w/c 05 Oct76 h
Luke Bianco· 338hTyler Hocking· 138h
w/c 19 Oct38 h
Kyle Mancini· 338h
w/c 26 Oct76 h
Ben Hartley· 338hTyler Hocking· 138h
SWMSAccepted
CMP-1018 SWMS — Berth access platform, ladders & gates — marine Accepted
Prepared in JSEasy · submitted to and accepted by Flinders Ports. Compliance →
SharePointSynced
Co-Create › Projects › 26-1053 Flinders Ports — Berth access platform, ladders & gates — marine
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client