Stage
Complete
ITP progress
8 / 8
hold points 4 / 4 signed
Job value
$58,786.35
Due
22 Oct 2026
High
Workshop route
✓ Queued
✓ Cutting
✓ Fabrication
✓ Welding
✓ Finishing
● Complete
Complete — heat number minted
Details
PRJ-2026-408 · Hansen Yuncken
| Quantity | 1 |
| Material | Galvanised |
| Finish | Hot-dip galvanised |
| Assigned to | Peter Voulgaris |
| Due date | 22 Oct 2026 |
| Heat / traceability no. | HT-40777 |
| Project | PRJ-2026-408 · Item 2 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
8 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 19 Sep 2026 · 08:15 | |
| 2 | Material certificates / heat numbers recorded | Passed | Dean Roberts 18 Sep 2026 · 10:40 | |
| 3 | Cut list & set-out checked | Passed | Dean Roberts 19 Sep 2026 · 13:05 | |
| 4 | Fit-up inspection before welding HOLD POINT | Passed | Yang Li 22 Sep 2026 · 08:15 | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Passed | Anthony Reid 22 Sep 2026 · 14:30 | |
| 6 | Dimensional check against drawing | Passed | Anthony Reid 21 Sep 2026 · 08:15 | |
| 7 | Surface prep & coating inspection HOLD POINT | Passed | Yang Li 03 Oct 2026 · 10:40 | |
| 8 | Final release to site HOLD POINT | Passed | Yang Li 21 Sep 2026 · 08:15 |
Project item
Item 2 — Balustrade 2 — stair balustrade, hangar office (38 m)
PRJ-2026-408 · register status Site
Allowed vs actual hours
Factory176 h / 178 h 99%
Site154.5 h / 116 h 133%
Office39 h / 42 h 93%
Recent time on this item
05 Oct · Site · 06:07 – on the clock
—
05 Oct · Site · 06:06 – on the clock
—
29 Sep · Site · 06:13–14:58
8.3 h
28 Sep · Site · 06:20–14:37
7.8 h
25 Sep · Site · 06:11–14:32
7.9 h
25 Sep · Site · 06:06–14:45
8.2 h
24 Sep · Site · 06:12–14:48
8.1 h
22 Sep · Site · 06:20–14:55
8.1 h
22 Sep · Site · 06:13–14:37
7.9 h
22 Sep · Site · 06:09–15:08
8.5 h
21 Sep · Site · 06:04–14:47
8.2 h
21 Sep · Site · 06:02–15:07
8.6 h