Co-Create

26-1056 · PRJ-2026-408

AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
Demo 05 Oct 2026
← Register
26-1056 PRJ-2026-408 Fabrication PayApps

AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork

Client Hansen Yuncken Site Adelaide SA PM Craig Pearce Client PO HY-AIR7-PO-4471 Programme 07 Sep 2026 → 10 Nov 2026 Quote Q-2026-1056
Progress42%
Contract value (ex GST)
$436.2k
8 items · 1 variation
Claimed to date
$207.1k
47% of contract
Scheduled claims (draft)
$229.1k
2 staged · PayApps
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
2472 / 1347.9
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Balustrade 1 — mezzanine edge balustrade (64 m) $94,705.55 21.7% 100% · $94.7k HY-AIR7-PO-4471
287 / 271
186 / 181
66 / 61
21 Sep JC-2026-3070
ITP 8/8
2 Balustrade 2 — stair balustrade, hangar office (38 m) $58,786.35 13.5% 70% · $41.2k HY-AIR7-PO-4471
178 / 176
116 / 154.5
42 / 39
19 Oct JC-2026-3071
ITP 8/8
3 Handrails — galvanised to apron access (90 m) $33,491.00 7.7% 70% · $23.4k HY-AIR7-PO-4471
99 / 89
64 / 49.7
25 / 23
26 Oct JC-2026-3072
ITP 8/8
4 External bollards — galvanised, apron (24 no) $27,277.20 6.3% 50% · $13.6k HY-AIR7-PO-4471
79 / 110.2
51 / 0
21 / 18
19 Oct JC-2026-3073
ITP 3/8
5 Perforated panelling — plant screen enclosure $71,381.65 16.4% 40% · $28.6k HY-AIR7-PO-4471
217 / 101.4
140 / 0
50 / 41
02 Nov JC-2026-3074
ITP 3/8
6 Ships ladders, cages & roof access platform $56,442.45 12.9% 10% · $5.6k HY-AIR7-PO-4471
170 / 0
110 / 0
40 / 12
09 Nov JC-2026-3075
ITP 1/8
7 Grating walkways & landings — services gantry $83,497.70 19.1% 0% · $0 HY-AIR7-PO-4471
252 / 0
163 / 0
58 / 17
09 Nov JC-2026-3076
ITP 1/8
V1 Additional galvanised bollards to apron (6 no) $10,654.00 2.4% 0% · $0 VO-01
29 / 0
19 / 0
10 / 4
02 Nov —
Progress claims$207,135.22 claimed · $229,100.70 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4229 24% 19 Sep 2026 $113,924.37 PayApps Lodged in PayApps Paid
#2 · INV-2026-4230 24% 01 Oct 2026 $113,924.37 PayApps Lodged in PayApps Sent
#3 · INV-2026-4231 26% 20 Oct 2026 $126,005.39 PayApps Draft Draft
#4 · INV-2026-4232 26% 08 Nov 2026 $126,005.39 PayApps Draft Draft
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Jess — lodge claim before cut-off · Dean — ITP hold point sign-off on item 2
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Sam — issue rev C drawings by Wed · Tyler — book EWP for Thursday
Purchase orders4 · $38,136.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7130 InfraBuild Steel Centre 2 02 Oct 2026 $11,718.00 Received
PO-2026-7131 Coventry Fasteners 2 18 Sep 2026 $2,928.00 Received
PO-2026-7143 Coventry Fasteners 1 15 Sep 2026 $4,704.00 Received
PO-2026-7142 Bianco Steel 1 11 Sep 2026 $18,786.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
05 Oct 2026 Josh Kerr 4 Factory On now
05 Oct 2026 Anthony Reid 4 Factory On now
05 Oct 2026 Mitch Daly 5 Factory On now
05 Oct 2026 Peter Voulgaris 4 Factory On now
05 Oct 2026 Ryan Tsoukalas 4 Factory On now
05 Oct 2026 Tyler Hocking 2 Site On now
05 Oct 2026 Ben Hartley 2 Site On now
02 Oct 2026 Josh Kerr 5 Factory 3.9
02 Oct 2026 Kyle Mancini 3 Site 8.2
02 Oct 2026 Ben Hartley 3 Site 8.4
01 Oct 2026 Anthony Reid 5 Factory 4.1
01 Oct 2026 Josh Kerr 5 Factory 3.6
01 Oct 2026 Sam Nguyen V1 Office 4
01 Oct 2026 Kyle Mancini 3 Site 8.6
30 Sep 2026 Ryan Tsoukalas 5 Factory 4.1
Crew assigned
w/c 05 Oct144 h
Mitch Daly· 538hYang Li· V130hBen Hartley· 338hKyle Mancini· 338h
w/c 12 Oct174 h
Peter Voulgaris· 438hRyan Tsoukalas· 438hSam Nguyen· 630hYang Li· 530hKyle Mancini· 338h
w/c 19 Oct136 h
Mitch Daly· 438hRyan Tsoukalas· 438hSam Nguyen· V130hYang Li· 730h
w/c 26 Oct144 h
Mitch Daly· 538hSam Nguyen· 430hKyle Mancini· 338hLuke Bianco· 238h
Open the shift schedule →
SWMSAccepted
CMP-1019 SWMS — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metal Accepted
Prepared in JSEasy · submitted to and accepted by Hansen Yuncken. Compliance →
SharePointSynced
Co-Create › Projects › 26-1056 Hansen Yuncken — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Hansen Yuncken
Rob Mistry · rob@hansenyuncken.com.au
Adelaide SA · NET 45