AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
Client Hansen Yuncken Site Adelaide SA PM Craig Pearce Client PO HY-AIR7-PO-4471 Programme 07 Sep 2026 → 10 Nov 2026 Quote Q-2026-1056
Progress42%
Contract value (ex GST)
$436.2k
8 items · 1 variation
Claimed to date
$207.1k
47% of contract
Scheduled claims (draft)
$229.1k
2 staged · PayApps
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
2472 / 1347.9
factory · site · office
Progress claims$207,135.22 claimed · $229,100.70 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4229 | 24% | 19 Sep 2026 | $113,924.37 | PayApps | Lodged in PayApps | Paid |
| #2 · INV-2026-4230 | 24% | 01 Oct 2026 | $113,924.37 | PayApps | Lodged in PayApps | Sent |
| #3 · INV-2026-4231 | 26% | 20 Oct 2026 | $126,005.39 | PayApps | Draft | Draft |
| #4 · INV-2026-4232 | 26% | 08 Nov 2026 | $126,005.39 | PayApps | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Jess — lodge claim before cut-off · Dean — ITP hold point sign-off on item 2
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Sam — issue rev C drawings by Wed · Tyler — book EWP for Thursday
Purchase orders4 · $38,136.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7130 | InfraBuild Steel Centre | 2 | 02 Oct 2026 | $11,718.00 | Received |
| PO-2026-7131 | Coventry Fasteners | 2 | 18 Sep 2026 | $2,928.00 | Received |
| PO-2026-7143 | Coventry Fasteners | 1 | 15 Sep 2026 | $4,704.00 | Received |
| PO-2026-7142 | Bianco Steel | 1 | 11 Sep 2026 | $18,786.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 05 Oct 2026 | Josh Kerr | 4 | Factory | On now |
| 05 Oct 2026 | Anthony Reid | 4 | Factory | On now |
| 05 Oct 2026 | Mitch Daly | 5 | Factory | On now |
| 05 Oct 2026 | Peter Voulgaris | 4 | Factory | On now |
| 05 Oct 2026 | Ryan Tsoukalas | 4 | Factory | On now |
| 05 Oct 2026 | Tyler Hocking | 2 | Site | On now |
| 05 Oct 2026 | Ben Hartley | 2 | Site | On now |
| 02 Oct 2026 | Josh Kerr | 5 | Factory | 3.9 |
| 02 Oct 2026 | Kyle Mancini | 3 | Site | 8.2 |
| 02 Oct 2026 | Ben Hartley | 3 | Site | 8.4 |
| 01 Oct 2026 | Anthony Reid | 5 | Factory | 4.1 |
| 01 Oct 2026 | Josh Kerr | 5 | Factory | 3.6 |
| 01 Oct 2026 | Sam Nguyen | V1 | Office | 4 |
| 01 Oct 2026 | Kyle Mancini | 3 | Site | 8.6 |
| 30 Sep 2026 | Ryan Tsoukalas | 5 | Factory | 4.1 |
Crew assigned
w/c 05 Oct144 h
Mitch Daly· 538hYang Li· V130hBen Hartley· 338hKyle Mancini· 338h
w/c 12 Oct174 h
Peter Voulgaris· 438hRyan Tsoukalas· 438hSam Nguyen· 630hYang Li· 530hKyle Mancini· 338h
w/c 19 Oct136 h
Mitch Daly· 438hRyan Tsoukalas· 438hSam Nguyen· V130hYang Li· 730h
w/c 26 Oct144 h
Mitch Daly· 538hSam Nguyen· 430hKyle Mancini· 338hLuke Bianco· 238h
SWMSAccepted
CMP-1019 SWMS — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metal Accepted
Prepared in JSEasy · submitted to and accepted by Hansen Yuncken. Compliance →
SharePointSynced
Co-Create › Projects › 26-1056 Hansen Yuncken — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client