Stage
Fabrication
ITP progress
3 / 8
hold points 1 / 4 signed
Job value
$27,277.20
Due
25 Oct 2026
Urgent
Workshop route
✓ Queued
✓ Cutting
● Fabrication
Welding · hold
Finishing
Complete · hold
Hold point — “Fit-up inspection before welding” must be signed off before this job can move to Welding.
Details
PRJ-2026-408 · Hansen Yuncken
| Quantity | 1 |
| Material | 316 SS |
| Finish | Galvanised + 2-pack |
| Assigned to | Josh Kerr |
| Due date | 25 Oct 2026 |
| Heat / traceability no. | minted on completion |
| Project | PRJ-2026-408 · Item 4 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
3 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 26 Sep 2026 · 08:15 | |
| 2 | Material certificates / heat numbers recorded | Passed | Anthony Reid 27 Sep 2026 · 14:30 | |
| 3 | Cut list & set-out checked | Passed | Dean Roberts 16 Sep 2026 · 13:05 | |
| 4 | Fit-up inspection before welding HOLD POINT | Pending | — | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Pending | — | |
| 6 | Dimensional check against drawing | Pending | — | |
| 7 | Surface prep & coating inspection HOLD POINT | Pending | — | |
| 8 | Final release to site HOLD POINT | Pending | — |
Project item
Item 4 — External bollards — galvanised, apron (24 no)
PRJ-2026-408 · register status Factory
Allowed vs actual hours
Factory110.2 h / 79 h 139%
Site0 h / 51 h 0%
Office18 h / 21 h 86%
Recent time on this item
05 Oct · Factory · 06:40 – on the clock
—
05 Oct · Factory · 06:36 – on the clock
—
05 Oct · Factory · 06:34 – on the clock
—
05 Oct · Factory · 06:33 – on the clock
—
25 Sep · Office · 08:00–12:00
4 h
21 Sep · Factory · 06:32–10:30
4 h
21 Sep · Factory · 06:25–10:30
4.1 h
18 Sep · Factory · 11:00–15:01
3.5 h
18 Sep · Factory · 11:00–15:01
3.5 h
18 Sep · Factory · 11:00–15:11
3.7 h
18 Sep · Factory · 06:39–10:30
3.9 h
18 Sep · Factory · 06:35–10:30
3.9 h