Stage
Queued
ITP progress
1 / 8
hold points 1 / 4 signed
Job value
$56,442.45
Due
10 Nov 2026
Urgent
Workshop route
● Queued
Cutting
Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-408 · Hansen Yuncken
| Quantity | 1 |
| Material | Aluminium |
| Finish | Galvanised + 2-pack |
| Assigned to | Josh Kerr |
| Due date | 10 Nov 2026 |
| Heat / traceability no. | minted on completion |
| Project | PRJ-2026-408 · Item 6 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
1 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 23 Sep 2026 · 14:30 | |
| 2 | Material certificates / heat numbers recorded | Pending | — | |
| 3 | Cut list & set-out checked | Pending | — | |
| 4 | Fit-up inspection before welding HOLD POINT | Pending | — | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Pending | — | |
| 6 | Dimensional check against drawing | Pending | — | |
| 7 | Surface prep & coating inspection HOLD POINT | Pending | — | |
| 8 | Final release to site HOLD POINT | Pending | — |
Project item
Item 6 — Ships ladders, cages & roof access platform
PRJ-2026-408 · register status Office
Allowed vs actual hours
Factory0 h / 170 h 0%
Site0 h / 110 h 0%
Office12 h / 40 h 30%
Recent time on this item
08 Sep · Office · 08:00–12:00
4 h
07 Sep · Office · 08:00–16:30
8 h