Stage
Queued
ITP progress
1 / 8
hold points 1 / 4 signed
Job value
$61,582.00
Due
18 Oct 2026
High
Workshop route
● Queued
Cutting
Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-409 · Mossop Construction + Interiors
| Quantity | 1 |
| Material | Aluminium |
| Finish | Satin 316 finish |
| Assigned to | Anthony Reid |
| Due date | 18 Oct 2026 |
| Heat / traceability no. | minted on completion |
| Project | PRJ-2026-409 · Item 2 |
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
1 / 8 checks
| # | Check | Status | Signed | Sign off |
|---|---|---|---|---|
| 1 | Drawings approved for construction (IFC) HOLD POINT | Passed | Yang Li 28 Sep 2026 · 08:15 | |
| 2 | Material certificates / heat numbers recorded | Pending | — | |
| 3 | Cut list & set-out checked | Pending | — | |
| 4 | Fit-up inspection before welding HOLD POINT | Pending | — | |
| 5 | Weld visual inspection to AS/NZS 1554.1 | Pending | — | |
| 6 | Dimensional check against drawing | Pending | — | |
| 7 | Surface prep & coating inspection HOLD POINT | Pending | — | |
| 8 | Final release to site HOLD POINT | Pending | — |
Project item
Item 2 — Balustrade 1 — apartment balconies (82 m)
PRJ-2026-409 · register status Office
Allowed vs actual hours
Factory0 h / 187 h 0%
Site0 h / 121 h 0%
Office0 h / 44 h 0%
Recent time on this item
Nobody has clocked onto this item yet.