26-1057 PRJ-2026-409 Detailing PayApps
Feature stair & balustrades — Kent Town apartments
Client Mossop Construction + Interiors Site Hindmarsh SA PM Craig Pearce Client PO MCI-2026-0418 Programme 25 Sep 2026 → 26 Nov 2026 Quote Q-2026-1057
Progress10%
Contract value (ex GST)
$173.3k
4 items
Claimed to date
$17.5k
10% of contract
Scheduled claims (draft)
$155.8k
2 staged · PayApps
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
981 / 83.7
factory · site · office
Progress claims$17,499.00 claimed · $155,814.10 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4233 | 10% | 02 Oct 2026 | $19,248.90 | PayApps | Lodged in PayApps | Sent |
| #2 · INV-2026-4234 | 45% | 23 Oct 2026 | $85,697.76 | PayApps | Draft | Draft |
| #3 · INV-2026-4235 | 45% | 25 Oct 2026 | $85,697.76 | PayApps | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts
Programme reviewed against HC look-ahead. Shop drawings status confirmed.
Actions Tyler — book EWP for Thursday · Craig — chase galvaniser ETA
Purchase orders0 · $0.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| No purchase orders yet — raise one from an item above. | |||||
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 05 Oct 2026 | Dean Roberts | 3 | Factory | On now |
| 02 Oct 2026 | Sam Nguyen | 1 | Office | 4 |
| 30 Sep 2026 | Sam Nguyen | 1 | Office | 4 |
| 25 Sep 2026 | Yang Li | 4 | Office | 4 |
| 24 Sep 2026 | Peter Voulgaris | 3 | Factory | 3.9 |
| 24 Sep 2026 | Dean Roberts | 3 | Factory | 4 |
| 23 Sep 2026 | Josh Kerr | 3 | Factory | 4.1 |
| 23 Sep 2026 | Dean Roberts | 3 | Factory | 3.8 |
| 23 Sep 2026 | Peter Voulgaris | 3 | Factory | 4 |
| 23 Sep 2026 | Ryan Tsoukalas | 3 | Factory | 4 |
| 23 Sep 2026 | Josh Kerr | 3 | Factory | 4.1 |
| 23 Sep 2026 | Anthony Reid | 3 | Factory | 4.1 |
| 23 Sep 2026 | Mitch Daly | 3 | Factory | 4.1 |
| 22 Sep 2026 | Dean Roberts | 3 | Factory | 4.1 |
| 22 Sep 2026 | Ryan Tsoukalas | 3 | Factory | 4.3 |
Crew assigned
w/c 05 Oct30 h
Sam Nguyen· 230h
w/c 12 Oct76 h
Josh Kerr· 338hMitch Daly· 338h
w/c 19 Oct38 h
Dean Roberts· 338h
w/c 26 Oct38 h
Peter Voulgaris· 338h
SWMSSubmitted
CMP-1020 SWMS — Feature stair & balustrades — Kent Town apartments Submitted
Prepared in JSEasy · submitted to and accepted by Mossop Construction + Interiors. Compliance →
SharePointSynced
Co-Create › Projects › 26-1057 Mossop Construction + Interiors — Feature stair & balustrades — Kent Town apartments
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client