Co-Create

Job Card JC-2026-3080

Item 4 — Bin store gates & screens
Demo 05 Oct 2026
Stage
Queued
ITP progress
1 / 8
hold points 1 / 4 signed
Job value
$19,144.15
Due
10 Nov 2026
Normal
Workshop route
● Queued
Cutting
Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-409 · Mossop Construction + Interiors
Quantity1
Material316 SS
FinishGalvanised + 2-pack
Assigned toAnthony Reid
Due date10 Nov 2026
Heat / traceability no.minted on completion
ProjectPRJ-2026-409 · Item 4
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
1 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
20 Sep 2026 · 08:15
2
Material certificates / heat numbers recorded
Pending —
3
Cut list & set-out checked
Pending —
4
Fit-up inspection before welding
HOLD POINT
Pending —
5
Weld visual inspection to AS/NZS 1554.1
Pending —
6
Dimensional check against drawing
Pending —
7
Surface prep & coating inspection
HOLD POINT
Pending —
8
Final release to site
HOLD POINT
Pending —
Customer
Mossop Construction + Interiors
Hindmarsh SA
Project
PRJ-2026-409 · Job 26-1057
Project item
Item 4 — Bin store gates & screens
PRJ-2026-409 · register status Office
Allowed vs actual hours
Factory0 h / 54 h 0%
Site0 h / 35 h 0%
Office8 h / 15 h 53%
Labour & time →
Recent time on this item
Yang Li
25 Sep · Office · 08:00–12:00
4 h
Yang Li
18 Sep · Office · 08:00–12:00
4 h