Job Card JC-2026-3058

Item 2 — Walkway, handrail & kickplate to gantry
Demo 05 Oct 2026
Stage
Fabrication
ITP progress
4 / 8
hold points 2 / 4 signed
Job value
$71,595.15
Due
16 Oct 2026
Normal
Workshop route
✓ Queued
✓ Cutting
● Fabrication
Welding · hold
Finishing
Complete · hold
Details
PRJ-2026-403 · Nyrstar Port Pirie
Quantity1
Material316 SS
FinishGalvanised + 2-pack
Assigned toDean Roberts
Due date16 Oct 2026
Heat / traceability no.minted on completion
ProjectPRJ-2026-403 · Item 2
Inspection & test plan
ISO 9001 quality plan · hold points must be signed off before the job moves past them
4 / 8 checks
#CheckStatusSignedSign off
1
Drawings approved for construction (IFC)
HOLD POINT
Passed
Yang Li
02 Oct 2026 · 08:15
2
Material certificates / heat numbers recorded
Passed
Anthony Reid
19 Sep 2026 · 13:05
3
Cut list & set-out checked
Passed
Dean Roberts
01 Oct 2026 · 14:30
4
Fit-up inspection before welding
HOLD POINT
Passed
Yang Li
17 Sep 2026 · 10:40
5
Weld visual inspection to AS/NZS 1554.1
Pending —
6
Dimensional check against drawing
Pending —
7
Surface prep & coating inspection
HOLD POINT
Pending —
8
Final release to site
HOLD POINT
Pending —
Customer
Nyrstar Port Pirie
Port Pirie SA
Project
PRJ-2026-403 · Job 26-1043
Project item
Item 2 — Walkway, handrail & kickplate to gantry
PRJ-2026-403 · register status Factory
Allowed vs actual hours
Factory96.9 h / 217 h 45%
Site0 h / 140 h 0%
Office44 h / 50 h 88%
Labour & time →
Recent time on this item
Mitch Daly
02 Oct · Factory · 11:00–15:25
3.9 h
Peter Voulgaris
02 Oct · Factory · 06:39–10:30
3.9 h
Peter Voulgaris
01 Oct · Factory · 11:00–15:45
4.3 h
Yang Li
01 Oct · Office · 08:00–12:00
4 h
Mitch Daly
01 Oct · Factory · 06:39–10:30
3.9 h
Peter Voulgaris
01 Oct · Factory · 06:37–10:30
3.9 h
Peter Voulgaris
30 Sep · Factory · 11:00–15:10
3.7 h
Dean Roberts
29 Sep · Factory · 11:00–15:13
3.7 h
Ryan Tsoukalas
29 Sep · Factory · 06:26–10:30
4.1 h
Dean Roberts
28 Sep · Factory · 06:39–10:30
3.9 h
Peter Voulgaris
28 Sep · Factory · 06:29–10:30
4 h
Mitch Daly
28 Sep · Factory · 06:29–10:30
4 h