26-1043 PRJ-2026-403 Fabrication MYOB
Conveyor gantry & support steel — Port Pirie
Client Nyrstar Port Pirie Site Port Pirie SA PM Craig Pearce Client PO NYR-PP-23019 Programme 07 Sep 2026 → 10 Nov 2026 Quote Q-2026-1043
Progress42%
Contract value (ex GST)
$232.3k
2 items
Claimed to date
$69.7k
30% of contract
Scheduled claims (draft)
$162.6k
2 staged · MYOB
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1326 / 354.7
factory · site · office
Progress claims$69,681.94 claimed · $162,591.16 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4209 | 15% | 19 Sep 2026 | $38,325.07 | MYOB | Pushed to MYOB | Paid |
| #2 · INV-2026-4210 | 15% | 01 Oct 2026 | $38,325.07 | MYOB | Pushed to MYOB | Sent |
| #3 · INV-2026-4211 | 35% | 22 Oct 2026 | $89,425.14 | MYOB | Draft | Draft |
| #4 · INV-2026-4212 | 35% | 10 Nov 2026 | $89,425.14 | MYOB | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Programme reviewed against HC look-ahead. Shop drawings status confirmed.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Material delivery confirmed; galv turnaround on track.
Actions Dean — ITP hold point sign-off on item 2 · Craig — chase galvaniser ETA
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Material delivery confirmed; galv turnaround on track.
Actions Sam — issue rev C drawings by Wed · Tyler — book EWP for Thursday
Purchase orders4 · $58,080.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7114 | Coventry Fasteners | 2 | 03 Oct 2026 | $3,552.00 | Sent |
| PO-2026-7111 | Bianco Steel | 1 | 03 Oct 2026 | $32,256.00 | Sent |
| PO-2026-7112 | Coventry Fasteners | 1 | 17 Sep 2026 | $8,064.00 | Part-Received |
| PO-2026-7113 | Vulcan Steel | 2 | 12 Sep 2026 | $14,208.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 05 Oct 2026 | Sam Nguyen | 1 | Office | On now |
| 02 Oct 2026 | Dean Roberts | 1 | Factory | 4 |
| 02 Oct 2026 | Peter Voulgaris | 1 | Factory | 3.9 |
| 02 Oct 2026 | Mitch Daly | 2 | Factory | 3.9 |
| 02 Oct 2026 | Peter Voulgaris | 2 | Factory | 3.9 |
| 02 Oct 2026 | Anthony Reid | 1 | Factory | 3.9 |
| 02 Oct 2026 | Josh Kerr | 1 | Factory | 4 |
| 01 Oct 2026 | Peter Voulgaris | 2 | Factory | 4.3 |
| 01 Oct 2026 | Yang Li | 2 | Office | 4 |
| 01 Oct 2026 | Dean Roberts | 1 | Factory | 3.9 |
| 01 Oct 2026 | Mitch Daly | 2 | Factory | 3.9 |
| 01 Oct 2026 | Peter Voulgaris | 2 | Factory | 3.9 |
| 01 Oct 2026 | Anthony Reid | 1 | Factory | 4 |
| 30 Sep 2026 | Anthony Reid | 1 | Factory | 4.3 |
| 30 Sep 2026 | Peter Voulgaris | 2 | Factory | 3.7 |
Crew assigned
w/c 05 Oct114 h
Anthony Reid· 238hDean Roberts· 138hRyan Tsoukalas· 138h
w/c 12 Oct76 h
Anthony Reid· 238hDean Roberts· 138h
w/c 19 Oct38 h
Josh Kerr· 138h
w/c 26 Oct38 h
Josh Kerr· 138h
SWMSAccepted
CMP-1015 SWMS — Conveyor gantry & support steel — Port Pirie Accepted
Prepared in JSEasy · submitted to and accepted by Nyrstar Port Pirie. Compliance →
SharePointSynced
Co-Create › Projects › 26-1043 Nyrstar Port Pirie — Conveyor gantry & support steel — Port Pirie
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client