26-1041 PRJ-2026-401 Fabrication MYOB

Louvre screens & sunhoods — airport carpark facade

Client Badge Constructions Site Kent Town SA PM Craig Pearce Client PO BC-24-1187 Programme 07 Sep 2026 → 10 Nov 2026 Quote Q-2026-1041
Progress42%
Contract value (ex GST)
$140.2k
4 items
Claimed to date
$64.7k
46% of contract
Scheduled claims (draft)
$75.5k
1 staged · MYOB
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
793 / 431.6
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Aluminium louvre screen frames & blades — Type A $48,680.50 34.7% 30% · $14.6k BC-24-1187
145 / 97.8
94 / 0
35 / 31
12 Oct JC-2026-3051
ITP 5/8
2 Perimeter sunhoods & flashings — folded sheet $38,148.25 27.2% 50% · $19.1k BC-24-1187
113 / 103.1
73 / 0
28 / 23
19 Oct JC-2026-3052
ITP 4/8
3 Louvre screens — Type B to stair core $21,297.25 15.2% 10% · $2.1k BC-24-1187
63 / 0
41 / 0
18 / 5
19 Oct JC-2026-3053
ITP 1/8
4 Site install, access & fixings $32,109.95 22.9% 90% · $28.9k BC-24-1187
96 / 93
62 / 56.7
25 / 22
26 Oct JC-2026-3054
ITP 8/8
Progress claims$64,706.98 claimed · $75,528.98 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4201 23% 19 Sep 2026 $35,588.84 MYOB Pushed to MYOB Paid
#2 · INV-2026-4202 23% 01 Oct 2026 $35,588.84 MYOB Pushed to MYOB Sent
#3 · INV-2026-4203 54% 17 Oct 2026 $83,081.88 MYOB Draft Draft
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Programme reviewed against HC look-ahead. Shop drawings status confirmed.
Actions Craig — chase galvaniser ETA · Tyler — book EWP for Thursday
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Dean — ITP hold point sign-off on item 2 · Jess — lodge claim before cut-off
Purchase orders8 · $34,183.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7103 InfraBuild Steel Centre 2 03 Oct 2026 $7,395.00 Part-Received
PO-2026-7104 Coventry Fasteners 2 01 Oct 2026 $1,853.00 Part-Received
PO-2026-7105 Southern Steel Group 3 28 Sep 2026 $4,060.00 Sent
PO-2026-7108 Coventry Fasteners 4 27 Sep 2026 $1,574.00 Received
PO-2026-7102 Coventry Fasteners 1 18 Sep 2026 $2,379.00 Received
PO-2026-7101 Vulcan Steel 1 17 Sep 2026 $9,570.00 Received
PO-2026-7107 InfraBuild Steel Centre 4 16 Sep 2026 $6,325.00 Received
PO-2026-7106 Coventry Fasteners 3 11 Sep 2026 $1,027.00 Draft
Recent labourlast 15 clock-ons
DatePersonItemKindHours
02 Oct 2026 Anthony Reid 2 Factory 4.1
02 Oct 2026 Ryan Tsoukalas 1 Factory 4.2
02 Oct 2026 Mitch Daly 1 Factory 3.9
02 Oct 2026 Ryan Tsoukalas 2 Factory 4.1
02 Oct 2026 Dean Roberts 2 Factory 4.1
01 Oct 2026 Dean Roberts 1 Factory 4.1
01 Oct 2026 Mitch Daly 1 Factory 3.9
01 Oct 2026 Ryan Tsoukalas 1 Factory 3.7
01 Oct 2026 Josh Kerr 2 Factory 3.9
01 Oct 2026 Ryan Tsoukalas 1 Factory 4
01 Oct 2026 Tyler Hocking 4 Site 8
30 Sep 2026 Dean Roberts 1 Factory 4.1
30 Sep 2026 Josh Kerr 2 Factory 3.8
30 Sep 2026 Mitch Daly 2 Factory 3.7
30 Sep 2026 Mitch Daly 1 Factory 3.9
Crew assigned
w/c 05 Oct38 h
Peter Voulgaris· 238h
w/c 12 Oct38 h
Luke Bianco· 438h
w/c 19 Oct76 h
Anthony Reid· 238hPeter Voulgaris· 138h
w/c 26 Oct38 h
Ryan Tsoukalas· 238h
Open the shift schedule →
SWMSAccepted
CMP-1013 SWMS — Louvre screens & sunhoods — airport carpark facade Accepted
Prepared in JSEasy · submitted to and accepted by Badge Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1041 Badge Constructions — Louvre screens & sunhoods — airport carpark facade
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Badge Constructions
Nick Karagiannis · nick@badgeconstruct.com.au
Kent Town SA · NET 30