26-1041 PRJ-2026-401 Fabrication MYOB
Louvre screens & sunhoods — airport carpark facade
Client Badge Constructions Site Kent Town SA PM Craig Pearce Client PO BC-24-1187 Programme 07 Sep 2026 → 10 Nov 2026 Quote Q-2026-1041
Progress42%
Contract value (ex GST)
$140.2k
4 items
Claimed to date
$64.7k
46% of contract
Scheduled claims (draft)
$75.5k
1 staged · MYOB
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
793 / 431.6
factory · site · office
Progress claims$64,706.98 claimed · $75,528.98 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4201 | 23% | 19 Sep 2026 | $35,588.84 | MYOB | Pushed to MYOB | Paid |
| #2 · INV-2026-4202 | 23% | 01 Oct 2026 | $35,588.84 | MYOB | Pushed to MYOB | Sent |
| #3 · INV-2026-4203 | 54% | 17 Oct 2026 | $83,081.88 | MYOB | Draft | Draft |
Weekly project meetings
28 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Programme reviewed against HC look-ahead. Shop drawings status confirmed.
Actions Craig — chase galvaniser ETA · Tyler — book EWP for Thursday
21 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Tyler — book EWP for Thursday · Dean — ITP hold point sign-off on item 2
14 Sep 2026Matthew Warren, Craig Pearce, Tanya Fielke, Dean Roberts, Tyler Hocking
Variation pricing agreed in principle; awaiting VO.
Actions Dean — ITP hold point sign-off on item 2 · Jess — lodge claim before cut-off
Purchase orders8 · $34,183.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7103 | InfraBuild Steel Centre | 2 | 03 Oct 2026 | $7,395.00 | Part-Received |
| PO-2026-7104 | Coventry Fasteners | 2 | 01 Oct 2026 | $1,853.00 | Part-Received |
| PO-2026-7105 | Southern Steel Group | 3 | 28 Sep 2026 | $4,060.00 | Sent |
| PO-2026-7108 | Coventry Fasteners | 4 | 27 Sep 2026 | $1,574.00 | Received |
| PO-2026-7102 | Coventry Fasteners | 1 | 18 Sep 2026 | $2,379.00 | Received |
| PO-2026-7101 | Vulcan Steel | 1 | 17 Sep 2026 | $9,570.00 | Received |
| PO-2026-7107 | InfraBuild Steel Centre | 4 | 16 Sep 2026 | $6,325.00 | Received |
| PO-2026-7106 | Coventry Fasteners | 3 | 11 Sep 2026 | $1,027.00 | Draft |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 02 Oct 2026 | Anthony Reid | 2 | Factory | 4.1 |
| 02 Oct 2026 | Ryan Tsoukalas | 1 | Factory | 4.2 |
| 02 Oct 2026 | Mitch Daly | 1 | Factory | 3.9 |
| 02 Oct 2026 | Ryan Tsoukalas | 2 | Factory | 4.1 |
| 02 Oct 2026 | Dean Roberts | 2 | Factory | 4.1 |
| 01 Oct 2026 | Dean Roberts | 1 | Factory | 4.1 |
| 01 Oct 2026 | Mitch Daly | 1 | Factory | 3.9 |
| 01 Oct 2026 | Ryan Tsoukalas | 1 | Factory | 3.7 |
| 01 Oct 2026 | Josh Kerr | 2 | Factory | 3.9 |
| 01 Oct 2026 | Ryan Tsoukalas | 1 | Factory | 4 |
| 01 Oct 2026 | Tyler Hocking | 4 | Site | 8 |
| 30 Sep 2026 | Dean Roberts | 1 | Factory | 4.1 |
| 30 Sep 2026 | Josh Kerr | 2 | Factory | 3.8 |
| 30 Sep 2026 | Mitch Daly | 2 | Factory | 3.7 |
| 30 Sep 2026 | Mitch Daly | 1 | Factory | 3.9 |
Crew assigned
w/c 05 Oct38 h
Peter Voulgaris· 238h
w/c 12 Oct38 h
Luke Bianco· 438h
w/c 19 Oct76 h
Anthony Reid· 238hPeter Voulgaris· 138h
w/c 26 Oct38 h
Ryan Tsoukalas· 238h
SWMSAccepted
CMP-1013 SWMS — Louvre screens & sunhoods — airport carpark facade Accepted
Prepared in JSEasy · submitted to and accepted by Badge Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1041 Badge Constructions — Louvre screens & sunhoods — airport carpark facade
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client