26-1068 PRJ-2026-417 Complete Complete MYOB
Pedestrian bridge steel & balustrade
Client Detmold Group Site Brompton SA PM Craig Pearce Client PO PO 70612 Programme 03 Jul 2026 → 26 Jul 2026 Quote Q-2026-1068
Progress100%
Contract value (ex GST)
$80.0k
2 items
Claimed to date
$80.0k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
30%
from quote-book costings
Allowed / actual hours
454 / 440
factory · site · office
Progress claims$80,017.35 claimed · $0.00 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4250 | 33% | 13 Jul 2026 | $29,339.70 | MYOB | Pushed to MYOB | Paid |
| #2 · INV-2026-4251 | 33% | 20 Jul 2026 | $29,339.70 | MYOB | Pushed to MYOB | Paid |
| #3 · INV-2026-4252 | 33% | 27 Jul 2026 | $29,339.70 | MYOB | Pushed to MYOB | Paid |
Weekly project meetings
No minutes recorded yet.
Purchase orders4 · $19,561.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7185 | Coventry Fasteners | 1 | 11 Jul 2026 | $1,968.00 | Received |
| PO-2026-7187 | Coventry Fasteners | 2 | 10 Jul 2026 | $1,968.00 | Received |
| PO-2026-7186 | Vulcan Steel | 2 | 10 Jul 2026 | $7,875.00 | Received |
| PO-2026-7184 | Vulcan Steel | 1 | 05 Jul 2026 | $7,750.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 24 Jul 2026 | Peter Voulgaris | 1 | Factory | 8 |
| 24 Jul 2026 | Anthony Reid | 2 | Factory | 8 |
| 24 Jul 2026 | Tyler Hocking | 1 | Site | 8 |
| 24 Jul 2026 | Tyler Hocking | 2 | Site | 8 |
| 23 Jul 2026 | Sam Nguyen | 1 | Office | 2 |
| 23 Jul 2026 | Yang Li | 2 | Office | 4 |
| 23 Jul 2026 | Anthony Reid | 1 | Factory | 8 |
| 23 Jul 2026 | Anthony Reid | 2 | Factory | 3 |
| 23 Jul 2026 | Kyle Mancini | 1 | Site | 8 |
| 22 Jul 2026 | Yang Li | 1 | Office | 8 |
| 22 Jul 2026 | Sam Nguyen | 2 | Office | 8 |
| 22 Jul 2026 | Dean Roberts | 1 | Factory | 8 |
| 22 Jul 2026 | Mitch Daly | 2 | Factory | 8 |
| 22 Jul 2026 | Tyler Hocking | 1 | Site | 8 |
| 21 Jul 2026 | Yang Li | 1 | Office | 8 |
Crew assigned
No one assigned yet.
Open the shift schedule → SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Detmold Group. Compliance →
SharePointSynced
Co-Create › Projects › 26-1068 Detmold Group — Pedestrian bridge steel & balustrade
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client