Tank access stairs & landings
Demo 05 Oct 2026
← Register
26-1070 PRJ-2026-419 Complete Complete MYOB

Tank access stairs & landings

Client Detmold Group Site Brompton SA PM Craig Pearce Client PO PO 88571 Programme 03 Jul 2026 → 26 Jul 2026 Quote Q-2026-1070
Progress100%
Contract value (ex GST)
$236.1k
2 items
Claimed to date
$236.1k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1348 / 1305
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Handrails — tank access stairs & landings $117,760.45 49.9% 100% · $117.8k PO 88571
360 / 341
233 / 214
81 / 80
20 Jul —
2 Access platform — tank access stairs & landings $118,384.30 50.1% 100% · $118.4k PO 88571
360 / 359
233 / 237
81 / 74
20 Jul —
Progress claims$236,144.76 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4256 50% 13 Jul 2026 $129,879.62 MYOB Pushed to MYOB Paid
#2 · INV-2026-4257 50% 20 Jul 2026 $129,879.62 MYOB Pushed to MYOB Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders4 · $59,052.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7196 InfraBuild Steel Centre 2 11 Jul 2026 $23,622.00 Received
PO-2026-7197 Coventry Fasteners 2 10 Jul 2026 $5,904.00 Received
PO-2026-7194 Vulcan Steel 1 09 Jul 2026 $23,622.00 Received
PO-2026-7195 Coventry Fasteners 1 05 Jul 2026 $5,904.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
24 Jul 2026 Yang Li 2 Office 8
24 Jul 2026 Josh Kerr 1 Factory 8
24 Jul 2026 Ryan Tsoukalas 1 Factory 8
24 Jul 2026 Josh Kerr 1 Factory 8
24 Jul 2026 Mitch Daly 2 Factory 8
24 Jul 2026 Mitch Daly 2 Factory 8
24 Jul 2026 Luke Bianco 1 Site 8
24 Jul 2026 Ben Hartley 1 Site 8
24 Jul 2026 Luke Bianco 2 Site 8
24 Jul 2026 Kyle Mancini 2 Site 8
23 Jul 2026 Ryan Tsoukalas 1 Factory 8
23 Jul 2026 Josh Kerr 1 Factory 8
23 Jul 2026 Dean Roberts 2 Factory 8
23 Jul 2026 Josh Kerr 2 Factory 8
23 Jul 2026 Luke Bianco 1 Site 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Detmold Group. Compliance →
SharePointSynced
Co-Create › Projects › 26-1070 Detmold Group — Tank access stairs & landings
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Detmold Group
Peter Detmold · peter@detmoldgroup.com.au
Brompton SA · NET 30