26-1075 PRJ-2026-422 Complete Complete MYOB
Handrail package — hospital fitout
Client Dept for Infrastructure & Transport Site Walkerville SA PM Matthew Warren Client PO PO 33354 Programme 03 Jun 2026 → 26 Jun 2026 Quote Q-2026-1075
Progress100%
Contract value (ex GST)
$131.2k
3 items
Claimed to date
$131.2k
100% of contract
Scheduled claims (draft)
$0
0 staged · MYOB
Gross profit (items)
29.9%
from quote-book costings
Allowed / actual hours
738 / 732
factory · site · office
Progress claims$131,166.96 claimed · $0.00 scheduled
| Claim | % | Date | Amount (inc GST) | Channel | Sync | Status |
|---|---|---|---|---|---|---|
| #1 · INV-2026-4262 | 33% | 13 Jun 2026 | $48,094.55 | MYOB | Pushed to MYOB | Paid |
| #2 · INV-2026-4263 | 33% | 20 Jun 2026 | $48,094.55 | MYOB | Pushed to MYOB | Paid |
| #3 · INV-2026-4264 | 33% | 27 Jun 2026 | $48,094.55 | MYOB | Pushed to MYOB | Paid |
Weekly project meetings
No minutes recorded yet.
Purchase orders6 · $31,888.00 ex GST
| PO | Supplier | Item | Date | Subtotal | Status |
|---|---|---|---|---|---|
| PO-2026-7209 | Coventry Fasteners | 1 | 11 Jun 2026 | $2,128.00 | Received |
| PO-2026-7208 | InfraBuild Steel Centre | 1 | 11 Jun 2026 | $8,505.00 | Received |
| PO-2026-7213 | Coventry Fasteners | 3 | 08 Jun 2026 | $2,128.00 | Received |
| PO-2026-7211 | Coventry Fasteners | 2 | 08 Jun 2026 | $2,128.00 | Received |
| PO-2026-7212 | InfraBuild Steel Centre | 3 | 06 Jun 2026 | $8,494.00 | Received |
| PO-2026-7210 | Bianco Steel | 2 | 06 Jun 2026 | $8,505.00 | Received |
Recent labourlast 15 clock-ons
| Date | Person | Item | Kind | Hours |
|---|---|---|---|---|
| 26 Jun 2026 | Anthony Reid | 1 | Factory | 8 |
| 26 Jun 2026 | Anthony Reid | 2 | Factory | 8 |
| 26 Jun 2026 | Dean Roberts | 3 | Factory | 8 |
| 26 Jun 2026 | Ben Hartley | 1 | Site | 8 |
| 25 Jun 2026 | Peter Voulgaris | 1 | Factory | 8 |
| 25 Jun 2026 | Mitch Daly | 2 | Factory | 8 |
| 25 Jun 2026 | Peter Voulgaris | 3 | Factory | 8 |
| 24 Jun 2026 | Anthony Reid | 1 | Factory | 8 |
| 24 Jun 2026 | Josh Kerr | 2 | Factory | 8 |
| 24 Jun 2026 | Peter Voulgaris | 3 | Factory | 8 |
| 23 Jun 2026 | Josh Kerr | 1 | Factory | 8 |
| 23 Jun 2026 | Dean Roberts | 3 | Factory | 8 |
| 22 Jun 2026 | Josh Kerr | 1 | Factory | 8 |
| 22 Jun 2026 | Josh Kerr | 2 | Factory | 4 |
| 22 Jun 2026 | Anthony Reid | 3 | Factory | 8 |
Crew assigned
No one assigned yet.
Open the shift schedule → SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Dept for Infrastructure & Transport. Compliance →
SharePointSynced
Co-Create › Projects › 26-1075 Dept for Infrastructure & Transport — Handrail package — hospital fitout
- 01 Enquiry & Tender
- 02 Quote Book
- 03 Drawings (SolidWorks)
- 04 Purchasing
- 05 QA & ITPs
- 06 Safety & SWMS
- 07 Progress Claims
Client
Dept for Infrastructure & Transport
Anthony Doidge · anthony@deptforinfrast.com.au
Walkerville SA · NET 45