26-1076 · PRJ-2026-423

Loading dock steel & bollards
Demo 05 Oct 2026
← Register
26-1076 PRJ-2026-423 Complete Complete PayApps

Loading dock steel & bollards

Client Mossop Construction + Interiors Site Hindmarsh SA PM Craig Pearce Client PO MCI-2026-0418 Programme 03 Jun 2026 → 26 Jun 2026 Quote Q-2026-1076
Progress100%
Contract value (ex GST)
$340.0k
4 items
Claimed to date
$340.0k
100% of contract
Scheduled claims (draft)
$0
0 staged · PayApps
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1932 / 1925
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Handrails — loading dock steel & bollards $85,115.65 25% 100% · $85.1k MCI-2026-0418
257 / 260
167 / 161
59 / 56
22 Jun —
2 Access platform — loading dock steel & bollards $84,638.80 24.9% 100% · $84.6k MCI-2026-0418
257 / 248
167 / 170
59 / 55
22 Jun —
3 Stair & landings — loading dock steel & bollards $84,683.65 24.9% 100% · $84.7k MCI-2026-0418
257 / 246
167 / 170
59 / 60
22 Jun —
4 Screens — loading dock steel & bollards $85,547.65 25.2% 100% · $85.5k MCI-2026-0418
257 / 266
167 / 173
59 / 60
22 Jun —
Progress claims$339,985.76 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4265 50% 13 Jun 2026 $186,992.17 PayApps Lodged in PayApps Paid
#2 · INV-2026-4266 50% 20 Jun 2026 $186,992.17 PayApps Lodged in PayApps Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders8 · $85,096.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7216 InfraBuild Steel Centre 2 12 Jun 2026 $17,050.00 Received
PO-2026-7218 Bianco Steel 3 11 Jun 2026 $17,050.00 Received
PO-2026-7217 Coventry Fasteners 2 10 Jun 2026 $4,224.00 Received
PO-2026-7214 Vulcan Steel 1 09 Jun 2026 $17,050.00 Received
PO-2026-7221 Coventry Fasteners 4 08 Jun 2026 $4,224.00 Received
PO-2026-7219 Coventry Fasteners 3 08 Jun 2026 $4,224.00 Received
PO-2026-7215 Coventry Fasteners 1 07 Jun 2026 $4,224.00 Received
PO-2026-7220 Bianco Steel 4 05 Jun 2026 $17,050.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
26 Jun 2026 Dean Roberts 1 Factory 8
26 Jun 2026 Dean Roberts 1 Factory 8
26 Jun 2026 Anthony Reid 2 Factory 8
26 Jun 2026 Josh Kerr 2 Factory 8
26 Jun 2026 Josh Kerr 3 Factory 8
26 Jun 2026 Peter Voulgaris 3 Factory 8
26 Jun 2026 Mitch Daly 4 Factory 8
26 Jun 2026 Anthony Reid 4 Factory 8
26 Jun 2026 Tyler Hocking 1 Site 8
26 Jun 2026 Ben Hartley 2 Site 8
26 Jun 2026 Kyle Mancini 3 Site 8
26 Jun 2026 Tyler Hocking 4 Site 8
25 Jun 2026 Anthony Reid 1 Factory 8
25 Jun 2026 Dean Roberts 1 Factory 8
25 Jun 2026 Anthony Reid 2 Factory 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Mossop Construction + Interiors. Compliance →
SharePointSynced
Co-Create › Projects › 26-1076 Mossop Construction + Interiors — Loading dock steel & bollards
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Mossop Construction + Interiors
Sam Mossop · sam@mossopconstruc.com.au
Hindmarsh SA · NET 30