Access platforms & walkways — WWTP
Demo 05 Oct 2026
← Register
26-1080 PRJ-2026-426 Complete Complete PayApps

Access platforms & walkways — WWTP

Client Sarah Constructions Site Marleston SA PM Craig Pearce Client PO SC-PO-30552 Programme 03 May 2026 → 26 May 2026 Quote Q-2026-1080
Progress100%
Contract value (ex GST)
$265.6k
4 items
Claimed to date
$265.6k
100% of contract
Scheduled claims (draft)
$0
0 staged · PayApps
Gross profit (items)
30.1%
from quote-book costings
Allowed / actual hours
1512 / 1433
factory · site · office
ItemsHours shown allowed / actual · bar turns red when over the allowance
ItemDescriptionStatusValue%ClaimedClient PO Factory hSite hOffice hDue w/cJob card · ITP
1 Bollards — access platforms & walkways $66,303.10 25% 100% · $66.3k SC-PO-30552
201 / 193
130 / 119
47 / 43
25 May —
2 Balustrade — access platforms & walkways $66,148.10 24.9% 100% · $66.1k SC-PO-30552
201 / 182
130 / 120
47 / 48
25 May —
3 Handrails — access platforms & walkways $66,148.10 24.9% 100% · $66.1k SC-PO-30552
201 / 192
130 / 124
47 / 42
25 May —
4 Access platform — access platforms & walkways $67,012.10 25.2% 100% · $67.0k SC-PO-30552
201 / 200
130 / 125
47 / 45
25 May —
Progress claims$265,611.40 claimed · $0.00 scheduled
Claim%DateAmount (inc GST)ChannelSyncStatus
#1 · INV-2026-4272 50% 13 May 2026 $146,086.27 PayApps Lodged in PayApps Paid
#2 · INV-2026-4273 50% 20 May 2026 $146,086.27 PayApps Lodged in PayApps Paid
Weekly project meetings
No minutes recorded yet.
Purchase orders8 · $66,148.00 ex GST
POSupplierItemDateSubtotalStatus
PO-2026-7245 Coventry Fasteners 4 12 May 2026 $3,300.00 Received
PO-2026-7242 InfraBuild Steel Centre 3 12 May 2026 $13,206.00 Received
PO-2026-7241 Coventry Fasteners 2 12 May 2026 $3,300.00 Received
PO-2026-7240 Bianco Steel 2 12 May 2026 $13,206.00 Received
PO-2026-7239 Coventry Fasteners 1 09 May 2026 $3,300.00 Received
PO-2026-7244 Bianco Steel 4 07 May 2026 $13,206.00 Received
PO-2026-7243 Coventry Fasteners 3 06 May 2026 $3,300.00 Received
PO-2026-7238 Vulcan Steel 1 05 May 2026 $13,330.00 Received
Recent labourlast 15 clock-ons
DatePersonItemKindHours
26 May 2026 Sam Nguyen 1 Office 8
26 May 2026 Josh Kerr 1 Factory 8
26 May 2026 Ryan Tsoukalas 1 Factory 8
26 May 2026 Dean Roberts 2 Factory 8
26 May 2026 Anthony Reid 3 Factory 8
26 May 2026 Dean Roberts 3 Factory 8
26 May 2026 Peter Voulgaris 4 Factory 8
26 May 2026 Anthony Reid 4 Factory 8
26 May 2026 Kyle Mancini 1 Site 8
26 May 2026 Luke Bianco 2 Site 8
26 May 2026 Kyle Mancini 3 Site 8
26 May 2026 Ben Hartley 4 Site 5
25 May 2026 Sam Nguyen 1 Office 8
25 May 2026 Mitch Daly 1 Factory 8
25 May 2026 Josh Kerr 1 Factory 8
Crew assigned
No one assigned yet.
Open the shift schedule →
SWMSNot started
No SWMS submitted to the client for this project.
Prepared in JSEasy · submitted to and accepted by Sarah Constructions. Compliance →
SharePointSynced
Co-Create › Projects › 26-1080 Sarah Constructions — Access platforms & walkways — WWTP
  • 01 Enquiry & Tender
  • 02 Quote Book
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Sarah Constructions
David Petrusma · david@sarahconstruct.com.au
Marleston SA · NET 30