PO PO-2026-7130

InfraBuild Steel Centre · PRJ-2026-408 · Item 2
Demo 05 Oct 2026
← Purchasing
Status
Received
Total (inc GST)
$12,889.80
ETA
12 Oct 2026
raised 02 Oct 2026
Project
InfraBuild Steel Centre · 5d lead
Purchased for
Item 2 — Balustrade 2 — stair balustrade, hangar office (38 m)
PRJ-2026-408 · 26-1056 · Hansen Yuncken — AIR7000 Ph2 — RAAF Edinburgh hangar & facility metalwork
Site
Item value
$58,786.35
Materials allowed
$14,646.00
Factory hrs allowed
178 h
Due
22 Oct 2026
Other POs for this item: PO-2026-7131 (Coventry Fasteners, Received)
PO lines
ItemQtyReceivedUnit costAmount
PFC / SHS sections & checker plate189189$62.00$11,718.00
Subtotal$11,718.00
GST 10%$1,171.80
Total$12,889.80
Item 2 — Balustrade 2 — stair balustrade, hangar office (38 m)
Outlook correspondence0
InfraBuild Steel Centre · Daniel Moretti · sales@infrabuildsteelc.com.au
No emails filed against this PO yet