Item 1 — Q-2026-1054

Quote book · Adelaide Airport Ltd — Feature entry staircase & balustrade — terminal
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1054· Job 26-1054· Adelaide Airport Ltd· Estimator Tanya Fielke· Valid to 25 Aug 2026
‹ 1 of 3 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$34,096.00 Sell$42,620.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$27,280.00 $34,100.00
$
%
$6,816.00 $8,520.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours415 Cost$24,070.00 Sell$39,715.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$24,070.00 $39,715.50
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours269 Cost$17,216.00 Sell$28,406.40
DescriptionQtyUnitUnit costMargin CostSell
$
%
$17,216.00 $28,406.40
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$12,348.00 Sell$14,200.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$12,348.00 $14,200.20
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours93 Cost$7,416.00 Sell$11,242.80
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$4,608.00 $7,142.40
$
%
$1,800.00 $2,790.00
$
%
$720.00 $864.00
No allowances on this item.