26-1054 · Q-2026-1054

Adelaide Airport Ltd — Feature entry staircase & balustrade — terminal
Demo 05 Oct 2026
View project PRJ-2026-407 →
Job no
26-1054
Quote
Q-2026-1054
Client
Adelaide Airport Ltd
Estimator
Tanya Fielke
Quote date
26 Jul 2026
Valid to
25 Aug 2026
Status
Won
Enquiry
Direct to quote
This quote is won. Item outcomes are recorded and the quote book is locked — won items are now on project PRJ-2026-407.
Item schedule Outcome recorded for each item
3 / 25 items
ItemDescription MaterialsLabourContract Hrs F / S / O SellContributionGP% Outcome
1 Feature stringer stair — plate & CHS $34,096 $48,702 $12,348 415 / 269 / 93 $136,185 $89,741 30.1% Won Open sheet →
2 Glass-ready stainless balustrade — 54m $5,457 $8,416 $1,972 66 / 43 / 18 $22,603 $15,174 29.9% Won Open sheet →
3 Bronze-anodised handrail & fixings $9,111 $13,422 $3,283 111 / 72 / 28 $36,947 $24,553 30.1% Won Open sheet →
Quote total · ex GST $48,664 $70,540 $17,603 592 / 384 / 139 $195,735 $129,468 30.1%
Quote summary
Sell (ex GST)
$195,734.65
GST
$19,573.47
Total (inc GST)
$215,308.12
Materials$48,664.00
Labour$70,540.00
Contract services$17,603.00
Gross profit$58,927.65 30.1%
Contribution$129,467.65 66.1%
Money left in the business — excludes materials and contract services.
Allowed hours — carried into the project
592Factory
384Site
139Office
Won / lost position
Won$195,734.65
Lost$0.00
Pending$0.00
SharePoint folder
Created automatically
Set up with the job number when the quote was opened, with the standard templates in place.
Co-Create › Projects › 26-1054 Adelaide Airport Ltd — Feature entry staircase & balustrade — terminal
  • 01 Enquiry & Tender
  • 02 Quote Book 3 item sheets
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Adelaide Airport Ltd
Michelle Court · michelle@adelaideairpor.com.au
Adelaide Airport SA · ABN 97 406 730 985
08 8308 9211
Open customer →
Client acceptance
The client can accept from a link — no login. Accepting wins the quote: the won items go to the project register, each fabricated item gets a job card with its ITP, and the claims are staged.