Co-Create

Item 3 — Q-2026-1054

Quote book · Adelaide Airport Ltd — Feature entry staircase & balustrade — terminal
Demo 05 Oct 2026
← Back to quote
Item3
Q-2026-1054· Job 26-1054· Adelaide Airport Ltd· Estimator Tanya Fielke· Valid to 25 Aug 2026
‹ 3 of 3 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$9,111.00 Sell$11,388.75
DescriptionQtyUnitUnit costMargin CostSell
$
%
$7,287.00 $9,108.75
$
%
$1,824.00 $2,280.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours111 Cost$6,438.00 Sell$10,622.70
DescriptionQtyUnitUnit costMargin CostSell
$
%
$6,438.00 $10,622.70
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours72 Cost$4,608.00 Sell$7,603.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$4,608.00 $7,603.20
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$3,283.00 Sell$3,775.45
DescriptionQtyUnitUnit costMargin CostSell
$
%
$1,300.00 $1,495.00
$
%
$1,983.00 $2,280.45
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours28 Cost$2,376.00 Sell$3,556.80
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$1,224.00 $1,897.20
$
%
$504.00 $781.20
$
%
$360.00 $432.00
No allowances on this item.