26-1067 · Q-2026-1067

Detmold Group — Bin store, gates & bollards
Demo 05 Oct 2026
Job no
26-1067
Quote
Q-2026-1067
Client
Detmold Group
Estimator
Tanya Fielke
Quote date
03 Aug 2026
Valid to
02 Sep 2026
Status
Lost
Enquiry
Direct to quote
Item schedule One sheet per item — open a sheet to cost it, then mark each item won, lost or pending
4 / 25 items
ItemDescription MaterialsLabourContract Hrs F / S / O SellContributionGP% Outcome
1 Screens — bin store, gates & bollards $8,500 $12,552 $3,026 102 / 66 / 26 $34,386 $22,860 30%
Open sheet →
2 Bollards — bin store, gates & bollards $8,500 $12,732 $3,026 102 / 66 / 26 $34,602 $23,076 29.9%
Open sheet →
3 Balustrade — bin store, gates & bollards $8,500 $12,912 $3,026 102 / 66 / 26 $34,818 $23,292 29.8%
Open sheet →
4 Handrails — bin store, gates & bollards $8,500 $12,912 $3,026 102 / 66 / 26 $34,818 $23,292 29.8%
Open sheet →
Quote total · ex GST $34,000 $51,108 $12,104 408 / 264 / 104 $138,622 $92,518 29.9%
Each new item opens on its own sheet with a starter costing you can adjust.
Quote summary
Sell (ex GST)
$138,622.00
GST
$13,862.20
Total (inc GST)
$152,484.20
Materials$34,000.00
Labour$51,108.00
Contract services$12,104.00
Gross profit$41,410.00 29.9%
Contribution$92,518.00 66.7%
Money left in the business — excludes materials and contract services.
Allowed hours — carried into the project
408Factory
264Site
104Office
Won / lost position
Won$0.00
Lost$138,622.00
Pending$0.00
SharePoint folder
Created automatically
Set up with the job number when the quote was opened, with the standard templates in place.
Co-Create › Projects › 26-1067 Detmold Group — Bin store, gates & bollards
  • 01 Enquiry & Tender
  • 02 Quote Book 4 item sheets
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Detmold Group
Peter Detmold · peter@detmoldgroup.com.au
Brompton SA · ABN 14 253 305 143
0413 118 220
Open customer →
Client acceptance
The client can accept from a link — no login. Accepting wins the quote: the won items go to the project register, each fabricated item gets a job card with its ITP, and the claims are staged.