Co-Create

Item 3 — Q-2026-1076

Quote book · Mossop Construction + Interiors — Loading dock steel & bollards
Demo 05 Oct 2026
← Back to quote
Item3
Q-2026-1076· Job 26-1076· Mossop Construction + Interiors· Estimator Tanya Fielke· Valid to 11 Jul 2026
‹ 3 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$21,274.00 Sell$26,592.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$17,050.00 $21,312.50
$
%
$4,224.00 $5,280.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours257 Cost$14,906.00 Sell$24,594.90
DescriptionQtyUnitUnit costMargin CostSell
$
%
$14,906.00 $24,594.90
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours167 Cost$10,688.00 Sell$17,635.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$10,688.00 $17,635.20
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$7,691.00 Sell$8,844.65
DescriptionQtyUnitUnit costMargin CostSell
$
%
$3,100.00 $3,565.00
$
%
$4,591.00 $5,279.65
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours59 Cost$4,608.00 Sell$7,016.40
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,808.00 $4,352.40
$
%
$1,152.00 $1,785.60
$
%
$360.00 $432.00
No allowances on this item.