Co-Create

Item 3 — Q-2026-1044

Quote book · Sarah Constructions — Stainless handrail & grab-rail package — hospital
Demo 05 Oct 2026
← Back to quote
Item3
Q-2026-1044· Job 26-1044· Sarah Constructions· Estimator Tanya Fielke· Valid to 25 Sep 2026
‹ 3 of 3 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$1,557.00 Sell$1,946.25
DescriptionQtyUnitUnit costMargin CostSell
$
%
$1,248.00 $1,560.00
$
%
$309.00 $386.25
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours19 Cost$1,102.00 Sell$1,818.30
DescriptionQtyUnitUnit costMargin CostSell
$
%
$1,102.00 $1,818.30
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours12 Cost$768.00 Sell$1,267.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$768.00 $1,267.20
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$559.00 Sell$642.85
DescriptionQtyUnitUnit costMargin CostSell
$
%
$559.00 $642.85
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours10 Cost$1,620.00 Sell$2,196.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$288.00 $446.40
$
%
$144.00 $223.20
$
%
$900.00 $1,080.00
No allowances on this item.