Co-Create

Item 1 — Q-2026-1080

Quote book · Sarah Constructions — Access platforms & walkways — WWTP
Demo 05 Oct 2026
← Back to quote
Item1
Q-2026-1080· Job 26-1080· Sarah Constructions· Estimator Tanya Fielke· Valid to 04 Jun 2026
‹ 1 of 4 ›
Won
This quote is won — the sheet is locked. Allowed hours from it now drive labour tracking on the project.
1
Materials
Steel, plate, mesh, fixings — margin set per line
Cost$16,630.00 Sell$20,787.50
DescriptionQtyUnitUnit costMargin CostSell
$
%
$13,330.00 $16,662.50
$
%
$3,300.00 $4,125.00
No materials on this item.
2
Fabrication
Factory hours × rate — becomes the factory allowance
Hours201 Cost$11,658.00 Sell$19,235.70
DescriptionQtyUnitUnit costMargin CostSell
$
%
$11,658.00 $19,235.70
No fabrication on this item.
3
Installation
Site hours × rate — becomes the site allowance
Hours130 Cost$8,320.00 Sell$13,728.00
DescriptionQtyUnitUnit costMargin CostSell
$
%
$8,320.00 $13,728.00
No installation on this item.
4
Contract services
Outsourced work — paid out, so it comes off contribution
Cost$5,978.00 Sell$6,874.70
DescriptionQtyUnitUnit costMargin CostSell
$
%
$5,978.00 $6,874.70
No contract services on this item.
5
Allowances
Site measure, drafting, engineering, travel — office hours
Hours47 Cost$3,744.00 Sell$5,677.20
DescriptionQtyUnitUnit costMargin CostSell
$
%
$288.00 $446.40
$
%
$2,232.00 $3,459.60
$
%
$864.00 $1,339.20
$
%
$360.00 $432.00
No allowances on this item.