Co-Create

26-1046 · Q-2026-1046

Hansen Yuncken — Balustrades, handrails & access steel — WCH new build
Demo 05 Oct 2026
Job no
26-1046
Quote
Q-2026-1046
Client
Hansen Yuncken
Estimator
Tanya Fielke
Quote date
29 Sep 2026
Valid to
29 Oct 2026
Status
Sent
Item schedule One sheet per item — open a sheet to cost it, then mark each item won, lost or pending
7 / 25 items
ItemDescription MaterialsLabourContract Hrs F / S / O SellContributionGP% Outcome
1 Balustrade 1 — internal feature stair balustrade (48 m) $3,866 $10,832 $6,100 120 / 20 / 26 $29,209 $19,243 28.8%
Open sheet →
2 Balustrade 2 — frameless glass balustrade to void (22 m) $12,232 $5,244 $3,800 24 / 36 / 14 $27,507 $11,475 22.7%
Open sheet →
3 Handrails — Type-B to ramps & corridors (120 m) $3,624 $11,320 $5,600 96 / 64 / 8 $29,104 $19,880 29.4%
Open sheet →
4 External bollards — 316 SS (18 no) $5,580 $4,104 $3,200 36 / 18 / 7 $17,214 $8,434 25.2%
Open sheet →
5 Perforated panelling — feature screens to atrium (64 m²) $11,920 $10,256 $11,900 88 / 40 / 26 $44,996 $21,176 24.3%
Open sheet →
6 Steel access stair & landings — plant room $6,200 $16,312 $6,900 160 / 48 / 40 $41,826 $28,726 29.7%
Open sheet →
7 Supply loose fixings, ferrules & anchors Supply only $7,800 $0 $0 0 / 0 / 0 $9,750 $1,950 20%
Open sheet →
Quote total · ex GST $51,222 $58,068 $37,500 524 / 226 / 121 $199,607 $110,885 26.5%
Each new item opens on its own sheet with a starter costing you can adjust.
Quote summary
Sell (ex GST)
$199,606.50
GST
$19,960.65
Total (inc GST)
$219,567.15
Materials$51,222.00
Labour$58,068.00
Contract services$37,500.00
Gross profit$52,816.50 26.5%
Contribution$110,884.50 55.6%
Money left in the business — excludes materials and contract services.
Allowed hours — carried into the project
524Factory
226Site
121Office
Won / lost position
Won$0.00
Lost$0.00
Pending$199,606.50
SharePoint folder
Created automatically
Set up with the job number when the quote was opened, with the standard templates in place.
Co-Create › Projects › 26-1046 Hansen Yuncken — Balustrades, handrails & access steel — WCH new build
  • 01 Enquiry & Tender
  • 02 Quote Book 7 item sheets
  • 03 Drawings (SolidWorks)
  • 04 Purchasing
  • 05 QA & ITPs
  • 06 Safety & SWMS
  • 07 Progress Claims
Client
Hansen Yuncken
Rob Mistry · rob@hansenyuncken.com.au
Adelaide SA · ABN 49 746 594 498
0421 774 118
Progress claims lodged through PayApps
Open customer →
Client acceptance